SAP ABAP Message Class 61 Message Number 905 (No work centers were found with capacity requirements)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
Attribute
Message class | 61 | ||
Short Description | Error Messages for MRP | ||
Message Number | 905 | ||
Documentation status | |||
Authorization check Error Message | |||
Changed On |
Message Text
No work centers were found with capacity requirements
Help Document
Diagnosis
The capacity situation always refers to a work center.
The work centers displayed in the capacity situation are determined as follows:
- from material view;
if you branch into the capacity situation from the MRP list overview, capacities are displayed for all work centers that are effected from the planned orders in the MRP list of the material. - from planned order view;
if you branch into the capacity situation when processing a planned order, all work centers are displayed where capacity has been created by the planned order currently being processed.
System Response
If the scheduling of the appropriate planned orders creates no capacity requirements, no capacity situation is displayed.
Procedure
Check whether the scheduling of the planned orders creates capacity requirements. Capacity requirements are not created, for example, if the planned order was scheduled via the material master record, or if the creation of capacity requirements was switched off in Customizing.