SAP ABAP Message Class 61 Message Number 123 (Error determining planning periods for calendar &)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
Attribute
Message class | 61 | ||
Short Description | Error Messages for MRP | ||
Message Number | 123 | ||
Documentation status | |||
Authorization check Error Message | |||
Changed On |
Message Text
Error determining planning periods for calendar &
Help Document
Diagnosis
The system could not determine sufficient planning periods by the planning calendar to group requirements by planning calendar periods for all the requirements planned in the future.
System Response
When a material is planned by using the periodical lot size by planning calendar, sufficient periods must be calculated to group requirements by the planning calendar for all requirements.
Procedure
Rework the planning calendar with which the material was planned, which means calculate new planning calendar periods.
To do this, go to Customizing for MRP, under the activity Change PPC periods.
History
Last changed on/by | 20131127 | SAP | |
SAP Release Created in |