SAP ABAP Message Class 61 Message Number 098 (Maximum no. of order proposals per deadline exceeded)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
Attribute
Message class | 61 | ||
Short Description | Error Messages for MRP | ||
Message Number | 098 | ||
Documentation status | |||
Authorization check Error Message | |||
Changed On |
Message Text
Maximum no. of order proposals per deadline exceeded
Help Document
Diagnosis
If, due to the lot-sizing procedure, more order proposals are created per date than the limit set in Customizing, the system terminates the planning run.
This can occur, for example, if you use the lot-sizing procedure with fixed lot sizes. If this lot size is set too low to cover the usual requirement quantity, too many order proposals will be created for one date.
To avoid this happening, you can define a limit value in Customizing that limits the number of order proposals that are allowed to be created for one date. If this limit is exceeded, the system terminates the planning run.
Procedure
- Check the limit value for the maximum number of order proposals per date in Customizing for MRP. To do this, select Maintain entries.
- Or, check your lot-sizing procedure.