SAP ABAP Message Class 61 Message Number 047 (Change to a directly produced planned order - please note long text)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
⤷ PP-MRP-BD (Application Component) Master Data
⤷ MD0C (Package) Customizing R/3 Material Requirements Planning
Attribute
Message class | 61 | ||
Short Description | Error Messages for MRP | ||
Message Number | 047 | ||
Documentation status | Space: object requires documentation | ||
Authorization check Error Message | |||
Changed On | 20100310 |
Message Text
Change to a directly produced planned order - please note long text
Help Document
Diagnosis
Changes to planned orders for direct production should only be carried out by the planning run.
Only this can guarantee the match between requirement and order, which is necessary for direct production, as well as the completeness of the collective order.
A manual change to a planned order for direct production is, therefore, only sensible in exceptional cases. Such an exception could be, for example, the addition or deletion of a component.
Please note that the firming of the planned order is reset in the next MRP run for this material so that the consistency of the collective order can be guaranteed. Therefore, you should only change the planned order when you wish to convert the collective order immediately after.