| Data Element | STAT_COND |
| Short Description | Aggregation of activity data |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | CHAR1 | |
| Data Type | CHAR | Character String |
| Length | 1 | |
| Decimal Places | 0 | |
| Output Length | 1 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | ||
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 10 | Aggregate |
| Medium | 11 | Aggregation |
| Long | 0 | |
| Heading | 0 |
Documentation
Definition
The selected values are passed up the hierarchy to the cursor position according to the following rules:
- Planned date
The planned start date of the higher-level document is updated if it has not yet been set or is after the date of the dependent document.
The planned end date of the higher-level document is updated if it has not yet been set or is before the date of the dependent document.
Exception:
Neither planned start nor planned end date of the higher-level document lie between the planned start and planned end date of the dependent document.
- Actual date
The earliest start date of all dependent documents is the start date of the higher-level document.
The latest end date of all dependent documents is the end date of the higher-level document.
- Planned duration ( only in the procedure model )
The planned durations of the dependent documents are cumulated, and the planned duration of the higher-level document is set accordingly.
- Actual duration ( only in procedure model )
As for planned duration.
- Remaining duration ( only in the procedure model )
As for planned duration.
History
| Last changed by/on | SAP | 19960510 |
| SAP Release Created in |