SAP ABAP Data Element SMI_HORIZON_MID (Mid-Term Period in Days)
Hierarchy
EA-APPL (Software Component) SAP Enterprise Extension PLM, SCM, Financials
   SD-BF-SMI (Application Component) Supplier Managed Inventory
     VSMI (Package) Supplier-Managed Inventory (SNC-ERP)
Basic Data
Data Element SMI_HORIZON_MID
Short Description Mid-Term Period in Days  
Data Type
Category of Dictionary Type     Direct Type Entry
Type of Object Referenced     No Information
Domain / Name of Reference Type      
Data Type NUMC   Character string with only digits 
Length 3    
Decimal Places 0    
Output Length 3    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Mid-Term 
Medium 15 Middle Period 
Long 30 Mid-Term Period in Days 
Heading 35 Mid-Term Period in Days 
Documentation

Definition

The SMI_HORIZON_MID field indicates the number of days you use to specify the mid-term period for demand comparisons.

Use

You can specify the number of days in this field.

The supplier sets the short-term period to n days. The demand deviation check adds up the demands of the first n days of the material in the current message. The system compares this result with the sum of the first n days of the preceding message (of this material) while considering the upper and lower tolerances set in the profile for the short-term period.

The supplier also sets the mid-term period to m days. The demand deviation check adds up the demands of the days from n+1 up to n+m. The system compares this result with the corresponding days of the preceding message (of this material) while considering the upper and lower tolerances set in the profile for the mid-term period.

Dependencies

Example

The customer sends the following demand forecast:

Current Message         Preceding Message             Period

(sent on 02. Feb.):        (sent on 01. Feb):

        01. Feb.    10 pcs.

02. Feb.    15 pcs.    02. Feb.     10 pcs.        Short-term

03. Feb.    15 pcs.    03. Feb.     10 pcs.        Short-term

04. Feb.    15 pcs.    04. Feb.     10 pcs.        Short-term

05. Feb.    6 pcs.    05. Feb.     10 pcs.        Mid-term

06. Feb.    6 pcs.    06. Feb.     10 pcs.        Mid-term

07. Feb.    6 pcs.    07. Feb.     10 pcs.        Mid-term

08. Feb.    6 pcs.    08. Feb.     10 pcs.        Mid-term

09. Feb.    12 pcs.    09. Feb.     10 pcs.        Long-term

10. Feb.    12 pcs.    10. Feb.     10 pcs.        Long-term

11. Feb.    12 pcs.    11. Feb.     10 pcs.        Long-term

12. Feb.    12 pcs.    12. Feb.     10 pcs.        Long-term

13. Feb.    12 pcs.    13. Feb.     10 pcs.        Long-term

The supplier maintained 3 days for the short-term period with an upper tolerance of 40%, 4 days for the mid-term period with a lower tolerance of 30%, and 5 days for the long-term period with an upper tolerance of 30%.

The system carries out the following calculations:

Short-term period:

Sum of current demands, starting with the first day:

02. Feb. = 15 pcs., 03. Feb. = 15 pcs., 04. Feb. = 15 pcs. ==> 45 pcs.

Sum of preceding demands, comparing the same dates:

02. Feb. = 10 pcs. , 03. Feb. = 10 pcs., 04. Feb. = 10 pcs. ==> 30 pcs.

Result: The demands for the short-term period increased by 50%, which violates the tolerance of 40% specified for the short-term period.

Mid-term period:

Sum of current demands, starting with the first day after the short-term period:

05. Feb. = 6 pcs. , 06. Feb. = 6 pcs., 07. Feb. = 6 pcs., 08. Feb. = 6 pcs. ==> 24 pcs.

Sum of preceding demands, comparing the same dates:

05. Feb. = 10 pcs. , 06. Feb. = 10 pcs., 07. Feb. = 10 pcs., 08. Feb. = 10 pcs. ==> 40 pcs.

Result: The demands for the mid-term period decreased by 40%, which violates the tolerance of 30% specified for the mid-term period.

Long-term period:

Sum of current demands, starting with the first day after the mid-term period:

09. Feb. = 12 pcs. , 10. Feb. = 12 pcs., 11. Feb. = 12 pcs., 12. Feb. = 12 pcs., 13. Feb. = 12 pcs. ==> 60 pcs.

Sum of preceding demands, comparing the same dates:

09. Feb. = 10 pcs. , 10. Feb. = 10 pcs., 11. Feb. = 10 pcs., 12. Feb. = 10 pcs., 13. Feb. = 10 pcs. ==> 50 pcs.

Result: The demands for the long-term period increased by 20%, which does not violate the tolerance of 30% specified for the long-term period.

If the stop indicator is set, the processing of the item is stopped as soon as the demand change of at least one period leads to a tolerance violation.

History
Last changed by/on SAP  20100310 
SAP Release Created in 604