| Data Element | PPE_RESQUANT |
| Short Description | Number of Production Resources |
Data Type
| Category of Dictionary Type | D | Domain |
| Type of Object Referenced | No Information | |
| Domain / Name of Reference Type | MENG13 | |
| Data Type | QUAN | Quantity field, points to a unit field with format UNIT |
| Length | 13 | |
| Decimal Places | 3 | |
| Output Length | 17 | |
| Value Table |
Further Characteristics
| Search Help: Name | ||
| Search Help: Parameters | ||
| Parameter ID | ||
| Default Component name | RESOURCE_QUANTITY | |
| Change document | ||
| No Input History | ||
| Basic direction is set to LTR | ||
| No BIDI Filtering |
Field Label
| Length | Field Label | |
| Short | 5 | No. |
| Medium | 10 | Number |
| Long | 12 | Number |
| Heading | 8 | Number |
Documentation
Definition
Specifies how many production resources you have assigned to a line element.
Use
Using the production resource assignment to a line element in a line balance, you can map the available capacity of a line element. You calculate the available capacity of a line element with the following formula:
Available capacity of a line element = takt time x number of assigned production resources
You can increase the available capacity of a line element by increasing the number of assigned production resources.
Example
The takt time in line segment 1 is 1 min. You have already assigned a production resource. The average work content of the assigned activities is 5 min. In order to execute the assigned activities, you need to increase the number of production resources (for example, workers) to 5.