Hierarchy
⤷ SRM-EBP (Application Component) Enterprise Buyer
⤷ BBP_APPLICATION (Package) Structure Package EBP
⤷ ME (Package) Application development R/3 Purchasing
Basic Data
Data Element | LPAGG |
Short Description | Creation of FRC Schedules with Aggreg. Acc. to Planning Cal. |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | ANZTA | |
Data Type | NUMC | Character string with only digits |
Length | 3 | |
Decimal Places | 0 | |
Output Length | 3 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Plan. Cal. |
Medium | 20 | Aggr. Acc. to. Cal. |
Long | 40 | Aggregation Acc. to Planning Calendar |
Heading | 30 | Aggreg. Acc. to Plan. Calendar |
Supplementary Documentation - LPAGG 0001
Use
Enter the number of workdays for which you wish to aggregate schedule lines in accordance with the Planning calendar when creating scheduling agreement releases.
When you generate a release, all schedule lines falling within the periods specified in the planning calendar are aggregated and shown as the required quantity as per the first day of the period.
Examples
You wish to transmit aggregated schedules to your vendor twice-weekly.
You wish to transmit the scheduled quantities for the period Tuesday to Thursday as a schedule containing a single aggregate line on Tuesday.
You wish to transmit the scheduled quantities for the period Friday to Monday as a schedule containing a single aggregate line on Friday.
To achieve this, you have specified in the planning calendar that the start of the period is Tuesday and Friday in each case.
You have the following delivery schedule in your system:
Day of week Date Scheduled quantity
Tuesday 12.06. 100 pc
Wednesday 12.07. 100 pc
Thursday 12.08. 100 pc
Friday 12.09. 11 pc
Saturday 12.10. 11 pc
Monday 12.12. 11 pc
On the basis of the aforementioned settings, the following aggregated releases (single-line delivery schedules) will be transmitted to the vendor:
Day of week Date Scheduled quantity
Tuesday 12.06. 300 pc
Friday 12.09. 33 pc
Dependencies
You maintain the planning calendar in Customizing for production under Requirements planning -> Master data -> Maintain planning calendar.
History
Last changed by/on | SAP | 19980218 |
SAP Release Created in |