SAP ABAP Data Element FLG_EXP_C_ST (MPX export of constraints: Start before finish)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-ST-INT (Application Component) Interface to External Project Software
     CN_MPX_IF (Package) MPX Interface
Basic Data
Data Element FLG_EXP_C_ST
Short Description MPX export of constraints: Start before finish  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type XFELD    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Start
Medium 15 Start < finish 
Long 20 Start before finish 
Heading S
Documentation

Definition

Specifies that if there are constraints for both the start date and the finish date of an activity in the SAP system, the constraint for the start date is transfered to the MPX file.

Use

In the SAP system an activity can have constraints on both the start and finish dates.

However, in an MPX file only one constraint can be set per activity.

You use this indicator to decide that a constraint on the start date is more important than a constraint on the finish date.

Note

Since the constraints Finish from confirmation and Start from resource planning are not defined in MPX format, they are ignored for the transfer to a MPX file.

If one of the dates does not have a constraint, this indicator is not relevant.

History
Last changed by/on SAP  19990318 
SAP Release Created in