Hierarchy
⤷ CA-FIM-FCO (Application Component) Financial Conditions
⤷ FICO (Package) Financial Conditions
Basic Data
Data Element | FICO_ODATESHIFT |
Short Description | Working Day Shift |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | FICO_ODATESHIFT | |
Data Type | NUMC | Character string with only digits |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | WORKDAY_SHIFT | |
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Shift WrkD |
Medium | 15 | Work. Day Shift |
Long | 22 | Working Day Shift |
Heading | 15 | WDS |
Documentation
Use
Use the working day shift to determine if and when a date is shifted, if the day is not a working day according to the IMG activity Maintain Calendar .
In order to shift a working day you must specify one or more Factory Calendars in the respective conditions. The system shifts the date until it comes to a date which is a working day in all calendars.
Value range
The following values are available:
- 0 (No shift)
- 1 (Shift to next working day)
- 2 (Shift to next working day, modified)
Modified means that the date can only be shifted within the current month. If a shift would result in a date in the next or previous month, then the date is shifted in the opposite direction to the previous working day.
- 3 (Shift to previous working day)
- 4 (Shift to previous working day, modified)
Modified means that the date can only be shifted with the current month. If a shift would result in a date in the next or previous month, then the date is shifted in the opposite direction to the next working day.
Example
You want the system to shift 04/29/2007 (Sunday) to the next working day. The two factory calendars are defined as follows: Calendar 01 (German Standard) and Calendar NL (Netherlands).
Date Weekday Calendar 01 Calendar NL
04/27/2007 Friday Working Day Working day
04/28/2007 Saturday Not a working day Not a working day
04/29/2007 Sunday Holiday Not a working day
04/30/2007 Monday Working day Holiday
05/01/2007 Tuesday Holiday Working day
05/02/2007 Wednesday Working day Working day
You want to shift 04/29/2007 to the next working day (1 - Shift to next working day). The systems shifts to 05/02/2007 (Wednesday).
You want to shift 04/29/2007 to the next modified working day (2 - Shift to the next working day, modified) the system shifts back from 05/02/2007 in the other direction to the previous working day 04/27/2007.
History
Last changed by/on | SAP | 20110908 |
SAP Release Created in |