| Domain Name | PSHLP_GANTT_FIELDS_TD |
| Short Description | Gantt Fields |
Definition
| Data Type | NUMC | Character string with only digits |
| No. Characters | 2 | |
| Decimal Places | ||
| Output Length | 2 | |
| Conversion Routine | ||
| Sign | ||
| Lower Case |
Value Range
| # | Lower Limit | Upper Limit | Short Description |
|---|---|---|---|
| 1 | 01 | Description | |
| 2 | 02 | Basic Start Date | |
| 3 | 03 | Basic Finish Date | |
| 4 | 04 | Basic Duration | |
| 5 | 05 | Basic Duration Unit | |
| 6 | 06 | Basic Start Date (Earliest) | |
| 7 | 07 | Basic Finish Date (Earliest) | |
| 8 | 08 | Basic Start Date (Latest) | |
| 9 | 09 | Basic Finish Date (Latest) | |
| 10 | 10 | Basic Start Date (Scheduled) | |
| 11 | 11 | Basic Finish Date (Scheduled) | |
| 12 | 12 | Basic Release Date (Scheduled) | |
| 13 | 13 | Forecast Start Date | |
| 14 | 14 | Forecast Finish Date | |
| 15 | 15 | Forecast Duration | |
| 16 | 16 | Forecast Duration Unit | |
| 17 | 17 | Forecast Start Date (Earliest) | |
| 18 | 18 | Forecast Finish Date (Earliest) | |
| 19 | 19 | Forecast Scheduled Start | |
| 20 | 20 | Forecast Scheduled Finish | |
| 21 | 21 | Forecast Scheduled Release | |
| 22 | 22 | Actual Start Date | |
| 23 | 23 | Actual Finish Date | |
| 24 | 24 | Actual Duration | |
| 25 | 25 | Actual Duration Unit | |
| 26 | 26 | Tentative Start Date (Actual) | |
| 27 | 27 | Tentative Finish Date (Actual) | |
| 28 | 28 | Identification | |