SAP ABAP IMG Activity SIMG_CFMENUOPP1OMDC (Define Floats (Scheduling Margin Key))
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PP-MRP-BD (Application Component) Master Data
     MD0C (Package) Customizing R/3 Material Requirements Planning
IMG Activity
ID SIMG_CFMENUOPP1OMDC Define Floats (Scheduling Margin Key)  
Transaction Code S_ALR_87006143   IMG Activity: SIMG_CFMENUOPP1OMDC 
Created on 19981222    
Customizing Attributes SIMG_CFMENUOPP1OMDC   Define Floats (Scheduling Margin Key) 
Customizing Activity SIMG_CFMENUOPP1OMDC   Define Floats (Scheduling Margin Key) 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name SIMG_CFMENUOPP1OMDC    

In this step, you specify the floats for determining the basic dates of the planned orders. The floats are allocated to the material via the release period key in the material master record.

  • Opening period

    The opening period represents the number of workdays that are subtracted from the order start date in order to determine the order creation date. This time is used by the MRP controller as a float for converting planned orders into purchase requisitions or into production orders.

  • Float before production

    The float before production represents the number of workdays that are planned as a float between the order start date (planned start date) and the production start date (target start date).

    On the one hand, this float is intended to guarantee that delays in staging a material do not delay the production start. On the other hand, the production dates can be brought forward by means of the float to cope with capacity bottlenecks.

  • Float after production

    The float after production should provide a float for the production process to cope with any disruptions so that there is no danger that the planned finish date will be exceeded. You plan the float after production between order finish date (planned finish date) and scheduled end (target finish date).

  • Release period

    The release period represents the number of workdays that are subtracted from the order start date in order to determine the production order release. The release period is only relevant for production order management.

Recommendation

The opening period should reflect the processing time the MRP controller needs to convert planned orders into purchase requisitions or production orders. The opening period should be at least as long as the interval between two MRP intervals, so that all planned orders can be taken into account during the conversion.

Actions

Specify the floats.

Business Attributes
ASAP Roadmap ID 203   Establish Master Data 
Mandatory / Optional 1   Mandatory activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG SIMG_CFMENUOPP1OMDC 0 HLA0006451 O HLA0006451 O HLA0006431 O HLA0006250  
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
V436A V - View SM30 02 Floats for Scheduling 
History
Last changed by/on SAP  19981222 
SAP Release Created in