Hierarchy
⤷ PP-CRP-LVL (Application Component) Capacity Leveling
⤷ CY0C (Package) Customizing Capacity Planning
IMG Activity
ID | SIMG_CFMENUOLPKOPD2 | Define time profile |
Transaction Code | S_ALR_87003766 | IMG Activity: SIMG_CFMENUOLPKOPD2 |
Created on | 19981222 | |
Customizing Attributes | SIMG_CFMENUOLPKOPD2 | Define time profile |
Customizing Activity | SIMG_CFMENUOLPKOPD2 | Define Time Profile |
Document
Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
Document Name | SIMG_CFMENUOLPKOPD2 |
In this step you define time profiles for capacity leveling and the extended evaluation.
With the time profile, you specify various important time periods:
- Database read period
The database read period specifies the period in which capacity requirements are read from the database. All requirements are accessed which are partially or completely within the database read period.
- Evaluation period
The evaluation period specifies the period over which data is formatted and displayed. The evaluation period must lie within the database read period.
- Planning period
The planning period defines the period in which the SAP system can carry out planning. The planning period is smaller than or equal to the evaluation period.
You cannot move operations outside the planning period. Equally, when automatic finite scheduling is carried out for an operation the system only searches for a new date within the planning period.
Date for dispatching backlog
The date for dispatching the backlog is of importance in period-related planning.
You use the date for dispatching the backlog to determine the date backlogs are to be allocated.
The following types of entry are available:
- Actual date specifications
- These date specifications (for example, calendar day, calendar year) are only useful in the profiles in exceptional cases.
- Relative date specifications
- These date specifications (for example, number of calendar days, number of calendar years) are always calculated from the current day.
- For every period, you can specify in what form you want to enter the date by using the respective field "Type of entry".
Example
Evaluation period
Type of entry J (calendar month)
Start date 0
Finish date 2
Current date: 06/09/1994
In this case, the evaluation is carried out for the period from 6/1/1994 until 8/31/1994.
Note
- Specifications in posting periods and factory calendar days are not possible since a plant would have to be specified in this case.
- You cannot delete the time profiles that are contained in the standard system.
Standard settings
Time profiles are predefined in the SAP standard package.
Actions
Define time profiles according to your requirements.
Business Attributes
ASAP Roadmap ID | 207 | Establish Reporting |
Mandatory / Optional | 2 | Optional activity |
Critical / Non-Critical | 2 | Non-critical |
Country-Dependency | A | Valid for all countries |
Assigned Application Components
Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
---|---|---|---|---|
SIMG | SIMG_CFMENUOLPKOPD2 | 0 | HLA0006233 O HLA0006256 O HLA0006651 |
Maintenance Objects
Maintenance object type | C | Customizing Object |
Assigned objects | ||||||
---|---|---|---|---|---|---|
Customizing Object | Object Type | Transaction Code | Sub-object | Do not Summarize | Skip Subset Dialog Box | Description for multiple selections |
V_TCY33 | V - View | OPD2 | 02 | Capacity Leveling - Time Profile |
History
Last changed by/on | SAP | 19981222 |
SAP Release Created in |