SAP ABAP IMG Activity SIMG_CFMENUOLMDOMI1 (Define Safety Stock Availability)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PP-MRP-BD (Application Component) Master Data
     MD0C (Package) Customizing R/3 Material Requirements Planning
IMG Activity
ID SIMG_CFMENUOLMDOMI1 Define Safety Stock Availability  
Transaction Code S_ALR_87000746   IMG Activity: SIMG_CFMENUOLMDOMI1 
Created on 19981222    
Customizing Attributes SIMG_CFMENUOLMDOMI1   Define Safety Stock Availability 
Customizing Activity SIMG_CFMENUOPP1OMI1   Define Safety Stock Availability 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name SIMG_CFMENUOLMDOMI1    

In this step, you define the percentage of the safety stock to be available for planning. This function is used to avoid a situation where orders proposals are created unnecessarily by the system to cover small shortage quantities.

In MRP, the system usually carries out the lot-size calculation for every shortage and creates an appropriate order proposal or - if already available - a firm receipt with a rescheduling proposal.

However, it does not always make sense for a new order proposal to be created for every small shortage. These order proposals must all be managed, converted, placed in stock and settled. If you want to save yourself this effort, you can make a portion of the safety stock available for planning. This has the following consequences:

  • An order proposal is not created until the stock level has fallen below the safety stock available for planning
  • If the shortage exceeds the portion of safety stock available for planning, then the system creates an order proposal in the planning run that covers this requirement and that also replenishes the safety stock.
  • The portion of the safety stock available for planning can only be determined using the MRP group. Therefore, to determine that a certain percentage of the safety stock of a particular material is to be available for planning, this material must have been given the appropriate MRP group in the material master record.

Example:

                           Mat. 1         Mat. 2         Mat. 3
------------------------------------------------------------------------
Safety stock:              100 pc         100 pc          100 pc
available for planning:      0%            50%             50%

Shortage quantity            1 pc           1 pc           51 pc

Order proposal quantity
for lot-for-lot order qty    1 pc           0 pc           51 pc

Actions

Define per plant and per MRP group the percentage of the safety stock that is to be available for planning.

Business Attributes
ASAP Roadmap ID 204   Establish Functions and Processes 
Mandatory / Optional 1   Mandatory activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG SIMG_CFMENUOLMDOMI1 0 HLA0006803 Consumption-Based Planning (See Also PP-MRP) 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
V_438M_S V - View SM30 02 Safety Stock Availability 
History
Last changed by/on SAP  19981222 
SAP Release Created in