ID INM_SET_DATE_NAMES BAdI: Specify Default Dates for Object Navigator  
Transaction Code S_X1D_36000073   (empty) 
Created on 20100802    
Customizing Attributes INM_SET_DATE_NAMES   BAdI: Specify Default Dates for Object Navigator 
Customizing Activity INM_SET_DATE_NAMES   BAdI: Specify Default Dates for Object Navigator 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name INM_SET_DATE_NAMES_DEFAULT_ON    

Use

This Business Add-In (BAdI) is used in the object navigator of the following SAP Portfolio and Project Management objects:

  • Project
  • Phase
  • Task
  • Item
  • Initiative

You can specify special dates as start and finish for the objects within the object navigator.

Depending on the object, the following dates are possible:

  • Project: Calculated start or finish, fixed start or finish, forecasted start or finish
  • Phase: Calculated early start or finish, calculated late start or finish, fixed start or finish, forecasted start or finish
  • Task: Calculated early start or finish, calculated early start or finish, fixed start or finish, forecasted start or finish
  • Item: Actual start or finish, planned start or finish, forecasted start or finish
  • Initiative: Actual start or finish, planned start or finish, forecasted start or finish

To specify new dates, you have to deactivate the code lines for the current default dates and activate the two new code lines for the new dates. Do not change other code in the BAdI.

The BAdI contains the following default settings:

  • Project: Calculated start or finish
  • Phase: Earliest start or latest finish
  • Task: Earliest start or latest finish
  • Item: Planned start or finish
  • Initiative: Planned start or finish

Requirements

Standard settings

For more information about the standard settings (filters, single or multiple uses), see the Enh. Spot Element Definitions tab in the BAdI Builder (transaction SE18).

Activities

For information about implementing BAdIs as part of the Enhancement Concept, see SAP Library for SAP NetWeaver under BAdIs - Embedding in the Enhancement Framework.

Example

Business Attributes
ASAP Roadmap ID 204   Establish Functions and Processes 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 