SAP ABAP IMG Activity EFFR_US_013 (BAdI : Determine Cost Object Validity)
Hierarchy
EA-HRRXX (Software Component) Sub component EA-HRRXX of EA-HR
   PA-PA-US-EFR (Application Component) Effort Reporting
     PAOC_PAD_US_EFR (Package) HR USA: Effort Reporting
IMG Activity
ID EFFR_US_013 BAdI : Determine Cost Object Validity  
Transaction Code S_P7H_77000090   (empty) 
Created on 20061219    
Customizing Attributes EFFR_US   Maintain Equal Values for Cost Distribution and Effort Percentages 
Customizing Activity EFFR_US_013   BAdI : Determine Cost Object Validity 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name HRPADUS_EFFREP_GET_VALIDITY    

Use

This Business Add-In (Add-In) is used in the Effort Reporting component.

This Add-In enables you to determine the validity of cost objects used in effort reporting. The system calls this BAdI to retrieve the validity of the cost objects.

The standard SAP system uses master data to determine the validity of cost objects. For example, if the cost object is Cost Center then the system determines its validity using Cost Management. But if you want to define customer specific logic to determine the validity of cost objects, you ca do so using this Add-in.

Requirements

You should only carry out this step if both of the following points apply:

  • The SAP standard processes do not suit your needs
  • You are a competent ABAP/4 programmer

Standard settings

In the standard system, the Business Add-In is not activated.

Activities

  1. After calling up the IMG activity, a dialog box appears, in which the existing implementations are displayed. Choose Change, and proceed as follows:
  2. From the tab index, choose Interface.
  3. Save your entries, and assign the implementation to a development class.
  4. Place the cursor on the method, and double-click to enter method processing.
  5. Enter the coding for the implementation between the statements method <Interface name> ~ <Name of method> and end method.
  6. Save and implement your coding. Return to the Edit Implementation screen.
  7. Save the entries on the Edit Implementation screen.

Note

You can also change an implementation, and then activate it at a later time. In such a case, end the processing stage at this point.

  1. Choose Activate.
  2. The coding you stored in the method will be run when the application program is executed.

Example

Business Attributes
ASAP Roadmap ID 204   Establish Functions and Processes 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency I   Valid for countries specified 
Maintenance Objects
Maintenance object type E   Business Add-In - Definition 
History
Last changed by/on SAP  20070313 
SAP Release Created in 600