SAP ABAP IMG Activity /MRSS/C_DPR_ASG (Define Threshold for "Partially Planned" Status)
Hierarchy
☛MRSS_NW (Software Component) SAP Multiresource Scheduling for SAP Net ⤷PM-WOC (Application Component) Maintenance Processing ⤷/MRSS/DPR (Package) MRS Interface for Cprojects
Hypertext: Object Class - Class to which a document belongs.
Document Name
/MRSS/C_DPR_ASG
Use
In this Customizing activity, you specify the percentage by which demands for a role have to be covered by assignments before the system changes the demand status in the planning board from "Partially Planned" to "Planned". This affects demands from cProject roles. To determine the degree of coverage for a cProject role, the system compares the work of the role with the total duration of the assignments.
Requirements
Standard settings
Activities
Example
You have entered 80% as the threshold value for cProject roles. For a corresponding role, the total work is 100 hours. As soon as relevant assignments are created with a total of 80 hours work for the role demand(s), the demand status changes from "Partially Planned" to "Planned". This is also the case if no assignment has been created for the associated demand.