Table/Structure Field list used by SAP ABAP Program RCNKBEDR (Project Info System: Excel Control Table for Cap. Reqmt.s Overview)
SAP ABAP Program
RCNKBEDR (Project Info System: Excel Control Table for Cap. Reqmt.s Overview) is using
| # | Object Type | Object Name | Object Description | Note |
|---|---|---|---|---|
| 1 | KBEDR - PENDU | Forecast finish / time | ||
| 2 | KBEDR - REMNE | Unit for work | ||
| 3 | KBEDR - PSPID | Project definition | ||
| 4 | KBEDR - PRPOS | Identification for an investment program position | ||
| 5 | KBEDR - PRNAM | Investment program name | ||
| 6 | KBEDR - PRCTR | Profit Center | ||
| 7 | KBEDR - POSID | Work Breakdown Structure Element (WBS Element) | ||
| 8 | KBEDR - PLSCN | Planning Scenario of Long-Term Planning | ||
| 9 | KBEDR - PLNUM | Planned order number | ||
| 10 | KBEDR - PERTXT | Formatted Name of Employee or Applicant | ||
| 11 | KBEDR - PERNR | Personnel Number | ||
| 12 | KBEDR - REMNW | Remaining work | ||
| 13 | KBEDR - PENDD | Forecast finish / date | ||
| 14 | KBEDR - PEDZ | Forecast finish time of operation from confirmation | ||
| 15 | KBEDR - PEDD | Forecast finish date of operation from confirmation | ||
| 16 | KBEDR - PDAU | Forecasted duration of activity from confirmation | ||
| 17 | KBEDR - PDAE | Unit of the forecasted duration from the confirmation | ||
| 18 | KBEDR - OFMNW | Forecasted work (actual + remaining) | ||
| 19 | KBEDR - ODAUR | Remaining duration of activity | ||
| 20 | KBEDR - ODAUE | Unit for remaining duration | ||
| 21 | KBEDR - MGVRG | Operation Quantity | ||
| 22 | KBEDR - USE05 | User field: Unit for quantity fields | ||
| 23 | KBEDR - WERKS | Plant | ||
| 24 | KBEDR - VSNUMMER | Number or description of a version | ||
| 25 | KBEDR - VSGRUPPE | Group for a project version | ||
| 26 | KBEDR - VORNR | Activity number in network and standard network | ||
| 27 | KBEDR - VORBEI | Duration After Earliest Scheduled Start | ||
| 28 | KBEDR - VERZUG | Duration After Latest Scheduled Finish | ||
| 29 | KBEDR - VEINH | Unit for Duration of the Delay | ||
| 30 | KBEDR - UVORN | Activity element number (work/external/general costs) | ||
| 31 | KBEDR - USR05 | User field for quantity (length 10.3) | ||
| 32 | KBEDR - USR04 | User field for quantity (length 10.3) | ||
| 33 | KBEDR - ABARBD | Confirmation: Degree of processing | ||
| 34 | KBEDR - USE04 | User field: Unit for quantity fields | ||
| 35 | KBEDR - TYPKZ | Type of object causing the load (order category) | ||
| 36 | KBEDR - SSTAU | Latest start / time | ||
| 37 | KBEDR - SSTAD | Latest start / date | ||
| 38 | KBEDR - SPLIT | Split number | ||
| 39 | KBEDR - SPAETER | Actual Finish/Planned Finish After Latest Scheduled Finish | ||
| 40 | KBEDR - SENDU | Latest finish / time | ||
| 41 | KBEDR - SENDD | Latest finish / date | ||
| 42 | KBEDR - RSTUF | Reduction level which reduces operation lead time | ||
| 43 | KBEDR - BEAZE | Unit of measure for processing time | ||
| 44 | KBEDR - FSTAU | Earliest start / time | ||
| 45 | KBEDR - FSTAD | Earliest start / date | ||
| 46 | KBEDR - FRUEHER | Actual start is before earliest scheduled start | ||
| 47 | KBEDR - FENDU | Earliest finish /time | ||
| 48 | KBEDR - FENDD | Earliest finish /date | ||
| 49 | KBEDR - DAUNO | Normal duration of the activity | ||
| 50 | KBEDR - DAUNE | Normal duration/unit | ||
| 51 | KBEDR - BSTKZ | Indicator rqmts.record is confirmed (cap.availability check) | ||
| 52 | KBEDR - BEDSOLL | Capacity requirements scheduled for the operation/activity | ||
| 53 | KBEDR - BEDREST | Remaining capacity requirements scheduled for operation | ||
| 54 | KBEDR - LEKNW | Indicator: No remaining activity expected | ||
| 55 | KBEDR - AUTYPTXT | Display field for order category description | ||
| 56 | KBEDR - AUFNR | Order/Network number | ||
| 57 | KBEDR - ASVRG | Operation scrap | ||
| 58 | KBEDR - ARNUMMER | Archiving Session Number | ||
| 59 | KBEDR - ARBTXT | Short text for the CIM operating resource | ||
| 60 | KBEDR - ARBPL | Work center | ||
| 61 | KBEDR - ARBEI | Work involved in the activity | ||
| 62 | KBEDR - ARBEH | Unit for work | ||
| 63 | KBEDR - ABARBA | Confirmation: Degree of processing | ||
| 64 | KBEDR - IDAUR | Actual duration for confirmation | ||
| 65 | KBEDR - MEINH | Unit of measure for activity | ||
| 66 | KBEDR - KPVER | Distribution of capacity requirements (Planned/prod.order) | ||
| 67 | KBEDR - KEINH | Unit of of measure for displaying capacity requirements | ||
| 68 | KBEDR - KDPOS | Sales Document Item | ||
| 69 | KBEDR - KDAUF | Sales Document | ||
| 70 | KBEDR - KAPTXT | Capacity short text | ||
| 71 | KBEDR - KAPNM | Capacity name | ||
| 72 | KBEDR - KAPARTXT | Description of the capacity category | ||
| 73 | KBEDR - KAPAR | Capacity category | ||
| 74 | KBEDR - ISTAU | Actual start / time | ||
| 75 | KBEDR - ISTAD | Actual start / date | ||
| 76 | KBEDR - ISMNW | Actual work | ||
| 77 | KBEDR - ISDZ | Actual start: Execution/setup (time) | ||
| 78 | KBEDR - ISDD | Actual start: Execution (date) | ||
| 79 | KBEDR - IENDU | Actual finish / time | ||
| 80 | KBEDR - IENDD | Actual finish / date | ||
| 81 | KBEDR - IEDZ | Actual finish: Execution (time) | ||
| 82 | KBEDR - IEDD | Actual finish: Execution (date) | ||
| 83 | KBEDR - IDAUE | Unit for actual duration | ||
| 84 | SYST - TABIX | ABAP System Field: Row Index of Internal Tables |