Table/Structure Field list used by SAP ABAP Function Module PS_DETERMINE_LOG_KEY_FIGURES (Ermittlung der Logistikkennzahlen)
SAP ABAP Function Module
PS_DETERMINE_LOG_KEY_FIGURES (Ermittlung der Logistikkennzahlen) is using
# | Object Type | Object Name | Object Description | Note |
---|---|---|---|---|
![]() |
![]() |
|||
1 | ![]() |
ACT01 - ARBEH | Unit for work | |
2 | ![]() |
ACT01 - ARBEI | Work involved in the activity | |
3 | ![]() |
ACT01 - DAUNE | Normal duration/unit | |
4 | ![]() |
ACT01 - DAUNO | Normal duration of the activity | |
5 | ![]() |
ACT01 - EWDAN | Normal duration (from forecast) of activity | |
6 | ![]() |
ACT01 - EWDNE | Unit for forecast normal duration | |
7 | ![]() |
ACT01 - EWEND | Forecast finish date | |
8 | ![]() |
ACT01 - EWSTD | Forecasted start date for the activity | |
9 | ![]() |
ACT01 - FPAVD | Earliest scheduled start date (forecast) | |
10 | ![]() |
ACT01 - FPEDD | Earliest scheduled finish date (forecast) | |
11 | ![]() |
ACT01 - FSAVD | Earliest scheduled start: Execution (date) | |
12 | ![]() |
ACT01 - FSEDD | Earliest scheduled finish: Execution (date) | |
13 | ![]() |
ACT01 - IEDD | Actual finish: Execution (date) | |
14 | ![]() |
ACT01 - ISDD | Actual start: Execution (date) | |
15 | ![]() |
ACT01 - ISMNW | Actual work | |
16 | ![]() |
ACT01 - NTANF | Constraint for activity start (Basic) | |
17 | ![]() |
ACT01 - NTEND | Constraint for Finish of Activity (Basic) | |
18 | ![]() |
ACT01 - OFMNW | Forecasted work (actual + remaining) | |
19 | ![]() |
ACT01 - PDAE | Unit of the forecasted duration from the confirmation | |
20 | ![]() |
ACT01 - PDAU | Forecasted duration of activity from confirmation | |
21 | ![]() |
ACT01 - PEDD | Forecast finish date of operation from confirmation | |
22 | ![]() |
ACT01 - SPAVD | Latest scheduled start date (forecast) | |
23 | ![]() |
ACT01 - SPEDD | Latest scheduled finish date (forecast) | |
24 | ![]() |
ACT01 - SSAVD | Latest scheduled start: Execution (date) | |
25 | ![]() |
ACT01 - SSEDD | Latest scheduled finish: Execution (date) | |
26 | ![]() |
AFKO - AUFNR | Order Number | |
27 | ![]() |
AFKO - GETRI | Confirmed Order Finish Date | |
28 | ![]() |
AFKO - GLTPP | Finish date (forecast) | |
29 | ![]() |
AFKO - GLTPS | Scheduled forecast finish | |
30 | ![]() |
AFKO - GLTRI | Actual finish date | |
31 | ![]() |
AFKO - GLTRP | Basic finish date | |
32 | ![]() |
AFKO - GLTRS | Scheduled finish | |
33 | ![]() |
AFKO - GSTPP | Forecast start date | |
34 | ![]() |
AFKO - GSTPS | Scheduled forecast start | |
35 | ![]() |
AFKO - GSTRI | Actual start date | |
36 | ![]() |
AFKO - GSTRP | Basic start date | |
37 | ![]() |
AFKO - GSTRS | Scheduled start | |
38 | ![]() |
AFKO_INC - GETRI | Confirmed Order Finish Date | |
39 | ![]() |
AFKO_INC - GLTPP | Finish date (forecast) | |
40 | ![]() |
AFKO_INC - GLTPS | Scheduled forecast finish | |
41 | ![]() |
AFKO_INC - GLTRI | Actual finish date | |
42 | ![]() |
AFKO_INC - GLTRP | Basic finish date | |
43 | ![]() |
AFKO_INC - GLTRS | Scheduled finish | |
44 | ![]() |
AFKO_INC - GSTPP | Forecast start date | |
45 | ![]() |
AFKO_INC - GSTPS | Scheduled forecast start | |
46 | ![]() |
AFKO_INC - GSTRI | Actual start date | |
47 | ![]() |
AFKO_INC - GSTRP | Basic start date | |
48 | ![]() |
AFKO_INC - GSTRS | Scheduled start | |
49 | ![]() |
AFPO - AUFNR | Order Number | |
50 | ![]() |
AFVGD - ARBEH | Unit for work | |
51 | ![]() |
AFVGD - ARBEI | Work involved in the activity | |
52 | ![]() |
AFVGD - DAUNE | Normal duration/unit | |
53 | ![]() |
AFVGD - DAUNO | Normal duration of the activity | |
54 | ![]() |
AFVGD - EWDAN | Normal duration (from forecast) of activity | |
55 | ![]() |
AFVGD - EWDNE | Unit for forecast normal duration | |
56 | ![]() |
AFVGD - EWEND | Forecast finish date | |
57 | ![]() |
AFVGD - EWSTD | Forecasted start date for the activity | |
58 | ![]() |
AFVGD - FPAVD | Earliest scheduled start date (forecast) | |
59 | ![]() |
AFVGD - FPEDD | Earliest scheduled finish date (forecast) | |
60 | ![]() |
AFVGD - FSAVD | Earliest scheduled start: Execution (date) | |
61 | ![]() |
AFVGD - FSEDD | Earliest scheduled finish: Execution (date) | |
62 | ![]() |
AFVGD - IEDD | Actual finish: Execution (date) | |
63 | ![]() |
AFVGD - ISDD | Actual start: Execution (date) | |
64 | ![]() |
AFVGD - ISMNW | Actual work | |
65 | ![]() |
AFVGD - NTANF | Constraint for activity start (Basic) | |
66 | ![]() |
AFVGD - NTEND | Constraint for finish of activity (Basic) | |
67 | ![]() |
AFVGD - OFMNW | Forecasted work (actual + remaining) | |
68 | ![]() |
AFVGD - PDAE | Unit of the forecasted duration from the confirmation | |
69 | ![]() |
AFVGD - PDAU | Forecasted duration of activity from confirmation | |
70 | ![]() |
AFVGD - PEDD | Forecast finish date of operation from confirmation | |
71 | ![]() |
AFVGD - SPAVD | Latest scheduled start date (forecast) | |
72 | ![]() |
AFVGD - SPEDD | Latest scheduled finish date (forecast) | |
73 | ![]() |
AFVGD - SSAVD | Latest scheduled start: Execution (date) | |
74 | ![]() |
AFVGD - SSEDD | Latest scheduled finish: Execution (date) | |
75 | ![]() |
AFVVI - ARBEH | Unit for work | |
76 | ![]() |
AFVVI - ARBEI | Work involved in the activity | |
77 | ![]() |
AFVVI - DAUNE | Normal duration/unit | |
78 | ![]() |
AFVVI - DAUNO | Normal duration of the activity | |
79 | ![]() |
AFVVI - EWDAN | Normal duration (from forecast) of activity | |
80 | ![]() |
AFVVI - EWDNE | Unit for forecast normal duration | |
81 | ![]() |
AFVVI - EWEND | Forecast finish date | |
82 | ![]() |
AFVVI - EWSTD | Forecasted start date for the activity | |
83 | ![]() |
AFVVI - FPAVD | Earliest scheduled start date (forecast) | |
84 | ![]() |
AFVVI - FPEDD | Earliest scheduled finish date (forecast) | |
85 | ![]() |
AFVVI - FSAVD | Earliest scheduled start: Execution (date) | |
86 | ![]() |
AFVVI - FSEDD | Earliest scheduled finish: Execution (date) | |
87 | ![]() |
AFVVI - IEDD | Actual finish: Execution (date) | |
88 | ![]() |
AFVVI - ISDD | Actual start: Execution (date) | |
89 | ![]() |
AFVVI - ISMNW | Actual work | |
90 | ![]() |
AFVVI - NTANF | Constraint for activity start (Basic) | |
91 | ![]() |
AFVVI - NTEND | Constraint for finish of activity (Basic) | |
92 | ![]() |
AFVVI - OFMNW | Forecasted work (actual + remaining) | |
93 | ![]() |
AFVVI - PDAE | Unit of the forecasted duration from the confirmation | |
94 | ![]() |
AFVVI - PDAU | Forecasted duration of activity from confirmation | |
95 | ![]() |
AFVVI - PEDD | Forecast finish date of operation from confirmation | |
96 | ![]() |
AFVVI - SPAVD | Latest scheduled start date (forecast) | |
97 | ![]() |
AFVVI - SPEDD | Latest scheduled finish date (forecast) | |
98 | ![]() |
AFVVI - SSAVD | Latest scheduled start: Execution (date) | |
99 | ![]() |
AFVVI - SSEDD | Latest scheduled finish: Execution (date) | |
100 | ![]() |
AUFK - AUFNR | Order Number | |
101 | ![]() |
AUFK - AUTYP | Order category | |
102 | ![]() |
ELM_PS - KOKRS | Controlling Area | |
103 | ![]() |
PRPS - PSPNR | WBS Element | |
104 | ![]() |
PRTE - EDAUR | Forecasted length (duration) of the WBS element | |
105 | ![]() |
PRTE - EEINH | Unit for duration of WBS element planned dates | |
106 | ![]() |
PRTE - EENDE | Forecasted finish date of the WBS element | |
107 | ![]() |
PRTE - EETRM | Scheduled finish date (Forecast) | |
108 | ![]() |
PRTE - ESTRM | Scheduled start date (Forecast) | |
109 | ![]() |
PRTE - ESTRT | Forecasted start date of the WBS element | |
110 | ![]() |
PRTE - IDAUR | Actual length (duration) of the WBS element | |
111 | ![]() |
PRTE - IEINH | Unit for duration of actual WBS element dates | |
112 | ![]() |
PRTE - IENDE | Actual finish date of the WBS element | |
113 | ![]() |
PRTE - ISTRT | Actual start date for the WBS element | |
114 | ![]() |
PRTE - PDAUR | Length (duration) of the basic dates in the WBS element | |
115 | ![]() |
PRTE - PEINH | Unit for duration of basic WBS element dates | |
116 | ![]() |
PRTE - PENDE | WBS element: Basic finish date | |
117 | ![]() |
PRTE - PETRM | Scheduled finish (Basic) | |
118 | ![]() |
PRTE - POSNR | WBS Element | |
119 | ![]() |
PRTE - PSTRM | Scheduled start (Basic) | |
120 | ![]() |
PRTE - PSTRT | WBS element: Basic start date | |
121 | ![]() |
PRTE - VIEND | Tentative actual finish date for WBS element | |
122 | ![]() |
PRTE - VISTR | Tentative actual start date for WBS element | |
123 | ![]() |
PRTEINC - EDAUR | Forecasted length (duration) of the WBS element | |
124 | ![]() |
PRTEINC - EEINH | Unit for the length (duration) of the WBS element | |
125 | ![]() |
PRTEINC - EENDE | Forecasted finish date of the WBS element | |
126 | ![]() |
PRTEINC - EETRM | Scheduled finish date (Forecast) | |
127 | ![]() |
PRTEINC - ESTRM | Scheduled start date (Forecast) | |
128 | ![]() |
PRTEINC - ESTRT | Forecasted start date of the WBS element | |
129 | ![]() |
PRTEINC - IDAUR | Actual length (duration) of the WBS element | |
130 | ![]() |
PRTEINC - IEINH | Unit for the length (duration) of the WBS element | |
131 | ![]() |
PRTEINC - IENDE | Actual finish date of the WBS element | |
132 | ![]() |
PRTEINC - ISTRT | Actual start date for the WBS element | |
133 | ![]() |
PRTEINC - PDAUR | Length (duration) of the basic dates in the WBS element | |
134 | ![]() |
PRTEINC - PEINH | Unit for the length (duration) of the WBS element | |
135 | ![]() |
PRTEINC - PENDE | WBS element: Basic finish date | |
136 | ![]() |
PRTEINC - PETRM | Scheduled finish (Basic) | |
137 | ![]() |
PRTEINC - PSTRM | Scheduled start (Basic) | |
138 | ![]() |
PRTEINC - PSTRT | WBS element: Basic start date | |
139 | ![]() |
PRTEINC - VIEND | Tentative actual finish date for WBS element | |
140 | ![]() |
PRTEINC - VISTR | Tentative actual start date for WBS element | |
141 | ![]() |
PSEISACT01 - ARBEH | Unit for work | |
142 | ![]() |
PSEISACT01 - ARBEI | Work involved in the activity | |
143 | ![]() |
PSEISACT01 - DAUNE | Normal duration/unit | |
144 | ![]() |
PSEISACT01 - DAUNO | Normal duration of the activity | |
145 | ![]() |
PSEISACT01 - EWDAN | Normal duration (from forecast) of activity | |
146 | ![]() |
PSEISACT01 - EWDNE | Unit for forecast normal duration | |
147 | ![]() |
PSEISACT01 - EWEND | Forecast finish date | |
148 | ![]() |
PSEISACT01 - EWSTD | Forecasted start date for the activity | |
149 | ![]() |
PSEISACT01 - FPAVD | Earliest scheduled start date (forecast) | |
150 | ![]() |
PSEISACT01 - FPEDD | Earliest scheduled finish date (forecast) | |
151 | ![]() |
PSEISACT01 - FSAVD | Earliest scheduled start: Execution (date) | |
152 | ![]() |
PSEISACT01 - FSEDD | Earliest scheduled finish: Execution (date) | |
153 | ![]() |
PSEISACT01 - IEDD | Actual finish: Execution (date) | |
154 | ![]() |
PSEISACT01 - ISDD | Actual start: Execution (date) | |
155 | ![]() |
PSEISACT01 - ISMNW | Actual work | |
156 | ![]() |
PSEISACT01 - NTANF | Constraint for activity start (Basic) | |
157 | ![]() |
PSEISACT01 - NTEND | Constraint for Finish of Activity (Basic) | |
158 | ![]() |
PSEISACT01 - OFMNW | Forecasted work (actual + remaining) | |
159 | ![]() |
PSEISACT01 - PDAE | Unit of the forecasted duration from the confirmation | |
160 | ![]() |
PSEISACT01 - PDAU | Forecasted duration of activity from confirmation | |
161 | ![]() |
PSEISACT01 - PEDD | Forecast finish date of operation from confirmation | |
162 | ![]() |
PSEISACT01 - SPAVD | Latest scheduled start date (forecast) | |
163 | ![]() |
PSEISACT01 - SPEDD | Latest scheduled finish date (forecast) | |
164 | ![]() |
PSEISACT01 - SSAVD | Latest scheduled start: Execution (date) | |
165 | ![]() |
PSEISACT01 - SSEDD | Latest scheduled finish: Execution (date) | |
166 | ![]() |
PSEISAFKO - AUFNR | Order Number | |
167 | ![]() |
PSEISAFKO - GETRI | Confirmed Order Finish Date | |
168 | ![]() |
PSEISAFKO - GLTPP | Finish date (forecast) | |
169 | ![]() |
PSEISAFKO - GLTPS | Scheduled forecast finish | |
170 | ![]() |
PSEISAFKO - GLTRI | Actual finish date | |
171 | ![]() |
PSEISAFKO - GLTRP | Basic finish date | |
172 | ![]() |
PSEISAFKO - GLTRS | Scheduled finish | |
173 | ![]() |
PSEISAFKO - GSTPP | Forecast start date | |
174 | ![]() |
PSEISAFKO - GSTPS | Scheduled forecast start | |
175 | ![]() |
PSEISAFKO - GSTRI | Actual start date | |
176 | ![]() |
PSEISAFKO - GSTRP | Basic Start Date | |
177 | ![]() |
PSEISAFKO - GSTRS | Scheduled start | |
178 | ![]() |
PSEISAFPO - AUFNR | Order Number | |
179 | ![]() |
PSEISAUFK - AUFNR | Order Number | |
180 | ![]() |
PSEISAUFK - AUTYP | Order category | |
181 | ![]() |
PSEISELM_PS - EISKOKRS | Controlling Area | |
182 | ![]() |
PSEISLOG - DATFS | Earliest start date | |
183 | ![]() |
PSEISLOG - DATSE | Latest finish date | |
184 | ![]() |
PSEISLOG - EARBEH | Unit for work | |
185 | ![]() |
PSEISLOG - EARBEI | Work | |
186 | ![]() |
PSEISLOG - ECKEN | Finish date (from basic dates) | |
187 | ![]() |
PSEISLOG - ECKST | Basic start date | |
188 | ![]() |
PSEISLOG - EDAUEH | Actual duration unit | |
189 | ![]() |
PSEISLOG - EDAUER | Duration | |
190 | ![]() |
PSEISLOG - IARBEH | Unit for work | |
191 | ![]() |
PSEISLOG - IARBEI | Actual work | |
192 | ![]() |
PSEISLOG - IDAUEH | Actual duration unit | |
193 | ![]() |
PSEISLOG - IDAUER | Actual duration | |
194 | ![]() |
PSEISLOG - ISTEN | Actual finish date | |
195 | ![]() |
PSEISLOG - ISTST | Actual start date | |
196 | ![]() |
PSEISLOG - PARBEH | Unit for work | |
197 | ![]() |
PSEISLOG - PARBEI | Forecast work | |
198 | ![]() |
PSEISLOG - PDAUEH | Actual duration unit | |
199 | ![]() |
PSEISLOG - PDAUER | Forecast duration | |
200 | ![]() |
PSEISLOG - PROGEN | Forecast finish date | |
201 | ![]() |
PSEISLOG - PROGST | Forecast start date | |
202 | ![]() |
PSEISLOG - TEENFR | Earliest scheduled finish (from basic dates) | |
203 | ![]() |
PSEISLOG - TEENSP | Latest scheduled finish (from basic dates) | |
204 | ![]() |
PSEISLOG - TESTFR | Earliest scheduled start (from basic dates) | |
205 | ![]() |
PSEISLOG - TESTSP | Latest scheduled start (from basic dates) | |
206 | ![]() |
PSEISLOG - TPENFR | Earliest scheduled finish (from forecast dates) | |
207 | ![]() |
PSEISLOG - TPENSP | Latest scheduled finish (from forecast dates) | |
208 | ![]() |
PSEISLOG - TPSTFR | Earliest scheduled start (from forecast dates) | |
209 | ![]() |
PSEISLOG - TPSTSP | Latest scheduled start (from forecast dates) | |
210 | ![]() |
PSEISLOG - VARBEH | Unit for work | |
211 | ![]() |
PSEISLOG - VARBEI | Tentative work | |
212 | ![]() |
PSEISLOG - VDAUEH | Actual duration unit | |
213 | ![]() |
PSEISLOG - VDAUER | Tentative duration | |
214 | ![]() |
PSEISLOG - VORLEN | Tentative finish date | |
215 | ![]() |
PSEISLOG - VORLST | Tentative start date | |
216 | ![]() |
PSEISLOG2 - DATFS | Earliest start date | |
217 | ![]() |
PSEISLOG2 - DATSE | Latest finish date | |
218 | ![]() |
PSEISLOG2 - EARBEH | Unit for work | |
219 | ![]() |
PSEISLOG2 - EARBEI | Work | |
220 | ![]() |
PSEISLOG2 - ECKEN | Finish date (from basic dates) | |
221 | ![]() |
PSEISLOG2 - ECKST | Basic start date | |
222 | ![]() |
PSEISLOG2 - EDAUEH | Actual duration unit | |
223 | ![]() |
PSEISLOG2 - EDAUER | Duration | |
224 | ![]() |
PSEISLOG2 - IARBEH | Unit for work | |
225 | ![]() |
PSEISLOG2 - IARBEI | Actual work | |
226 | ![]() |
PSEISLOG2 - IDAUEH | Actual duration unit | |
227 | ![]() |
PSEISLOG2 - IDAUER | Actual duration | |
228 | ![]() |
PSEISLOG2 - ISTEN | Actual finish date | |
229 | ![]() |
PSEISLOG2 - ISTST | Actual start date | |
230 | ![]() |
PSEISLOG2 - PARBEH | Unit for work | |
231 | ![]() |
PSEISLOG2 - PARBEI | Forecast work | |
232 | ![]() |
PSEISLOG2 - PDAUEH | Actual duration unit | |
233 | ![]() |
PSEISLOG2 - PDAUER | Forecast duration | |
234 | ![]() |
PSEISLOG2 - PROGEN | Forecast finish date | |
235 | ![]() |
PSEISLOG2 - PROGST | Forecast start date | |
236 | ![]() |
PSEISLOG2 - TEENFR | Earliest scheduled finish (from basic dates) | |
237 | ![]() |
PSEISLOG2 - TEENSP | Latest scheduled finish (from basic dates) | |
238 | ![]() |
PSEISLOG2 - TESTFR | Earliest scheduled start (from basic dates) | |
239 | ![]() |
PSEISLOG2 - TESTSP | Latest scheduled start (from basic dates) | |
240 | ![]() |
PSEISLOG2 - TPENFR | Earliest scheduled finish (from forecast dates) | |
241 | ![]() |
PSEISLOG2 - TPENSP | Latest scheduled finish (from forecast dates) | |
242 | ![]() |
PSEISLOG2 - TPSTFR | Earliest scheduled start (from forecast dates) | |
243 | ![]() |
PSEISLOG2 - TPSTSP | Latest scheduled start (from forecast dates) | |
244 | ![]() |
PSEISLOG2 - VARBEH | Unit for work | |
245 | ![]() |
PSEISLOG2 - VARBEI | Tentative work | |
246 | ![]() |
PSEISLOG2 - VDAUEH | Actual duration unit | |
247 | ![]() |
PSEISLOG2 - VDAUER | Tentative duration | |
248 | ![]() |
PSEISLOG2 - VORLEN | Tentative finish date | |
249 | ![]() |
PSEISLOG2 - VORLST | Tentative start date | |
250 | ![]() |
PSEISPRPS - PSPNR | WBS Element | |
251 | ![]() |
PSEISPRTE - EDAUR | Forecasted length (duration) of the WBS element | |
252 | ![]() |
PSEISPRTE - EEINH | Unit for duration of WBS element planned dates | |
253 | ![]() |
PSEISPRTE - EENDE | Forecasted finish date of the WBS element | |
254 | ![]() |
PSEISPRTE - EETRM | Scheduled finish date (Forecast) | |
255 | ![]() |
PSEISPRTE - ESTRM | Scheduled start date (Forecast) | |
256 | ![]() |
PSEISPRTE - ESTRT | Forecasted start date of the WBS element | |
257 | ![]() |
PSEISPRTE - IDAUR | Actual length (duration) of the WBS element | |
258 | ![]() |
PSEISPRTE - IEINH | Unit for duration of actual WBS element dates | |
259 | ![]() |
PSEISPRTE - IENDE | Actual finish date of the WBS element | |
260 | ![]() |
PSEISPRTE - ISTRT | Actual start date for the WBS element | |
261 | ![]() |
PSEISPRTE - PDAUR | Length (duration) of the basic dates in the WBS element | |
262 | ![]() |
PSEISPRTE - PEINH | Unit for duration of basic WBS element dates | |
263 | ![]() |
PSEISPRTE - PENDE | WBS element: Basic finish date | |
264 | ![]() |
PSEISPRTE - PETRM | Scheduled finish (Basic) | |
265 | ![]() |
PSEISPRTE - POSNR | WBS Element | |
266 | ![]() |
PSEISPRTE - PSTRM | Scheduled start (Basic) | |
267 | ![]() |
PSEISPRTE - PSTRT | WBS element: Basic start date | |
268 | ![]() |
PSEISPRTE - VIEND | Tentative actual finish date for WBS element | |
269 | ![]() |
PSEISPRTE - VISTR | Tentative actual start date for WBS element | |
270 | ![]() |
PSEISRESB01 - BDTER | Requirements date for the component | |
271 | ![]() |
PSGEN - EXPDATE | PS key figure: export date | |
272 | ![]() |
PSGEN - EXPDATE | PS key figure: export date | SOURCE VALUE(I_EXPDATE) LIKE PSGEN-EXPDATE |
273 | ![]() |
PSGENLOG - CONARE | Controlling Area | |
274 | ![]() |
PSGENLOG - EXPDATE | PS key figure: export date | |
275 | ![]() |
PSGENLOG2 - EXPDATE | PS key figure: export date | |
276 | ![]() |
PSGENLOG2 - EXPDATE | PS key figure: export date | SOURCE VALUE(I_EXPDATE) LIKE PSGEN-EXPDATE |
277 | ![]() |
RESB - BDTER | Requirements date for the component | |
278 | ![]() |
RESB01 - BDTER | Requirements date for the component | |
279 | ![]() |
RESBD - BDTER | Requirements date for the component | |
280 | ![]() |
SYST - TABIX | ABAP System Field: Row Index of Internal Tables |