SAP ABAP Message Class PPECHK Message Number 314 (Action point &1 at line network &2 cannot be assigned to a line resource)
Hierarchy
☛
EA-IPPE (Software Component) SAP iPPE
⤷ AP-PPE (Application Component) Integrated Product and Process Engineering
⤷ CPPECHK (Package) Consistency Check of Production Version
⤷ AP-PPE (Application Component) Integrated Product and Process Engineering
⤷ CPPECHK (Package) Consistency Check of Production Version
Attribute
Message class | PPECHK | ||
Short Description | iPPE Consistency Check | ||
Message Number | 314 | ||
Documentation status | Space: object requires documentation | ||
Authorization check Error Message | |||
Changed On | 20040316 |
Message Text
Action point &1 at line network &2 cannot be assigned to a line resource
Help Document
Diagnosis
The action point at the start and end of line network cannot be assigned to a line resource because the line structure starts and ends either with parallel or alternative lines. In order for the Action Handler to determine the line resource assigned to an action point, there must be distinct starting and ending lines.
System Response
Procedure
Ensure that the line structure has distinct starting and ending lines, or, maintain action points at each starting and ending line, as required.
Procedure for System Administration
History
Last changed on/by | 20110810 | SAP | |
SAP Release Created in | 200 |