SAP ABAP Message Class PPEBAL Message Number 208 (Validity of line balance &1 exceeds the date 12.31.2037)
Hierarchy
☛
EA-IPPE (Software Component) SAP iPPE
⤷ AP-PPE (Application Component) Integrated Product and Process Engineering
⤷ CPPEBAL (Package) BAL-Specific iPPE Objects
⤷ AP-PPE (Application Component) Integrated Product and Process Engineering
⤷ CPPEBAL (Package) BAL-Specific iPPE Objects
Attribute
Message class | PPEBAL | ||
Short Description | Line Balance Message | ||
Message Number | 208 | ||
Documentation status | Space: object requires documentation | ||
Authorization check Error Message | |||
Changed On | 20060703 |
Message Text
Validity of line balance &1 exceeds the date 12.31.2037
Help Document
Diagnosis
You entered the from date in the validity of the line balance . However, the validity exceeds the date 12.31.2037. This maximum date is defined by the live cache because the live cache can only work until 12.31.2037 due to technical limitations.
System Response
The assignments between the components and the supply areas are made in the line resolution using the line balance. The validities of the component to supply area assignments are adapted to the maximum date of the live cache. Duplicates could be found here which cause problems when writing the supply area cluster to the live cache.
Procedure
Set the valid-from date of the line balance to before the 12.31.2037.
Procedure for System Administration
History
Last changed on/by | 20040316 | SAP | |
SAP Release Created in | 46C1 |