SAP ABAP Message Class /SAPPCE/PNV Message Number 207 ('Integrated Planning' not active for version &1 in fiscal year &2)
Hierarchy
EA-FIN (Software Component) EA-FIN
   PS-REV-CPR (Application Component) Construction Progress Report
     /SAPPCE/PNV (Package) Construction Progress Report and Valuation
Attribute
Message class /SAPPCE/PNV  
Short Description Construction Progress Report and Valuation    
Message Number 207  
Documentation status       Space: object requires documentation
Authorization check Error Message      
Changed On 20020228   
Message Text
'Integrated Planning' not active for version &1 in fiscal year &2
Help Document

Diagnosis

Integrated planning is not active. This must be active to be able to to update planned data for contract values, planned revenues or planned costs.

Integrated planning is active, if the indicator Integrated Planning is set both for the WBS elements and the CO version.

System Response

Procedure

Set the indicator Integrated Planning for the CO version and fiscal year in Customizing for Controlling under Maintain Versions in the detail view Settings per Fiscal Year.

Procedure for System Administration

History
Last changed on/by 20030113  SAP 
SAP Release Created in   470