SAP ABAP Message Class /SAPPCE/PNV Message Number 207 ('Integrated Planning' not active for version &1 in fiscal year &2)
Hierarchy
☛
EA-FIN (Software Component) EA-FIN
⤷ PS-REV-CPR (Application Component) Construction Progress Report
⤷ /SAPPCE/PNV (Package) Construction Progress Report and Valuation
⤷ PS-REV-CPR (Application Component) Construction Progress Report
⤷ /SAPPCE/PNV (Package) Construction Progress Report and Valuation
Attribute
Message class | /SAPPCE/PNV | ||
Short Description | Construction Progress Report and Valuation | ||
Message Number | 207 | ||
Documentation status | Space: object requires documentation | ||
Authorization check Error Message | |||
Changed On | 20020228 |
Message Text
'Integrated Planning' not active for version &1 in fiscal year &2
Help Document
Diagnosis
Integrated planning is not active. This must be active to be able to to update planned data for contract values, planned revenues or planned costs.
Integrated planning is active, if the indicator Integrated Planning is set both for the WBS elements and the CO version.
System Response
Procedure
Set the indicator Integrated Planning for the CO version and fiscal year in Customizing for Controlling under Maintain Versions in the detail view Settings per Fiscal Year.