SAP ABAP Message Class /SAPPCE/PNV Message Number 206 (Indicator 'Integrated Planning' not active for WBS element &1)
Hierarchy
EA-FIN (Software Component) EA-FIN
   PS-REV-CPR (Application Component) Construction Progress Report
     /SAPPCE/PNV (Package) Construction Progress Report and Valuation
Attribute
Message class /SAPPCE/PNV  
Short Description Construction Progress Report and Valuation    
Message Number 206  
Documentation status       Space: object requires documentation
Authorization check Error Message      
Changed On 20020227   
Message Text
Indicator 'Integrated Planning' not active for WBS element &1
Help Document

Diagnosis

Integrated planning is not active. This must be active to be able to update contract values, planned revenues or planned costs.

Integrated planning is active if indicator Integrated Planning is set for both the WBS element and the CO version.

System Response

Procedure

  • You can set the indicator for the WBS element.
    1. Call the Project Builder (transaction CJ20N).
    2. In the tree structure, select WBS element .
    3. Select tab page Control.
    4. Set indicator Integrated Planning.
    5. Save data.
  • You can also set the indicator Integrated Planning in the project profile. In Customizing for Project System select IMG activity Activate Integrate Planning for WBS Elements. This indicator will then be automatically transferred for all WBS elements for which you selected this project profile.

Procedure for System Administration

History
Last changed on/by 20030113  SAP 
SAP Release Created in   470