SAP ABAP Data Element WSRP_NETCH (Use Net Change Procedure)
Hierarchy
EA-RETAIL (Software Component) SAP Enterprise Extension Retail
   MM-CBP (Application Component) Consumption-Based Planning (See Also PP-MRP)
     WSRP (Package) Retail: Store Replenishment
Basic Data
Data Element WSRP_NETCH
Short Description Use Net Change Procedure  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type CHAR1_X    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Net Change 
Medium 20 Net Change Planning 
Long 40 Use Net Change Procedure 
Heading 50 Use Net Change Procedure 
Documentation

Definition

Indicator for using the net change method.

Use

The net change method only includes materials that have been subject to replenishment-relevant changes since requirements were last calculated.

The changes could include, for example, changes to stock or the replenishment parameters.

Using the net change method improves system performance. If you choose not to use the method, the requirement calculation is run for all materials that are active for replenishment.

Notes

If you choose to calculate target stock dynamically, using the net change version may result in some materials being excluded from your calculation.

Example

Start the requirement calculation function for a material, and calculate your target stock dynamically. Activate the net change method. Due to increasing forecasted sales, a higher target stock (calculated dynamically) is generated than when requirements were last calculated.

The material is not, however, included in the requirement calculation as no replenishment-relevant changes have been made since requirements were last calculated.

It is therefore recommended that you only use the net change method for materials whose target stock is calculated dynamically and for whom sales (and therefore stock changes) have been recorded since the requirement calculation was last run.

Dependencies

History
Last changed by/on SAP  20011002 
SAP Release Created in 46C