SAP ABAP Data Element /MRSS/T_SGE_DEM_PLANSTAT_DUR (Duration Logic for Planning Status Determination)
Hierarchy
MRSS_NW (Software Component) SAP Multiresource Scheduling for SAP Net
   PM-WOC-MO (Application Component) Maintenance Orders
     /MRSS/SGE (Package) Multiresource Planning: Scheduling Engine
Basic Data
Data Element /MRSS/T_SGE_DEM_PLANSTAT_DUR
Short Description Duration Logic for Planning Status Determination  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type /MRSS/_SGE_DEM_PLANSTAT_DUR    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Dur. Logic 
Medium 15 Duration Logic 
Long 20 Duration Logic 
Heading 14 Duration Logic 
Documentation

Definition

Use

You use this field to specify whether the system is to consider only the duration or the total work, that is, the duration multiplied by the number of resources, to determine the planning status for a demand.

Based on the setting you make here, the system also calculates the remaining duration for a demand (see example).

Dependencies

This field is only relevant if you have chosen either the DURA or COUNT option in the Det. Logic field.

Example

A demand requires 2 resources for 3 hours each (total work = 6 hours). The assignments´ total duration is 4 hours. In that case, the following applies:

  • If you choose 1 - Duration, the planning status for the demand is set to Planned and the remaining work is -1 hour.
  • If you choose 2 - Total Work, the planning status for the demand is set to Partially Planned and the remaining work is 2 hours.