SAP ABAP Data Element /MRSS/T_RM_FLIESSKZ (Indicator: continuous flow production)
Hierarchy
MRSS_NW (Software Component) SAP Multiresource Scheduling for SAP Net
   PM-WOC-CP (Application Component) Capacity and Resource Planning
     /MRSS/RMI_NW (Package) RM Integration Layer
Basic Data
Data Element /MRSS/T_RM_FLIESSKZ
Short Description Indicator: continuous flow production  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type XFELD    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name IND_CONT_FLOW_PRODUCTION   
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Cont. flow 
Medium 15 Cont. flow prod 
Long 20 Continuous flow prod 
Heading 10 ContFlow 
Documentation

Definition

You use this indicator to specify that operations always overlap (regardless of the reduction strategy of the operation) if the conditions for overlapping are fulfilled.

The system extends the lead time of all overlapping operations for which the indicator is set to the lead time of the longest operation.

Dependencies

  • Conditions for Overlaps/>

    During scheduling the system determines from the minimum send-ahead quantity and the minimum overlap time.

    • Whether the operations can overlap
    • An overlap is only permissible, if the time the operations overlap is larger than the minimum overlap time.
    • When is the start date of the following operation
    • If operations overlap, the next operation can start when the minimum send-ahead quantity has been produced. If a move is necessary, this is taken into account with the minimum move time.
      The following operation is scheduled so that no interruptions occur.
  • Additional Condition for Overlaps in Collective Orders

If you specify overlps for the last operation of an order, which is part of a collective order this operation can overlap with its successor in the superior order. The prerequisite for this is that there is no difference between the requirements date of the directly produced component and the basic finish date of the subordinate order.

History
Last changed by/on SAP  20141109 
SAP Release Created in 700