ID | ORPM_PROJECT_STAT | Define Portfolio Item Alerts |
Transaction Code | S_XSD_23000038 | (empty) |
Created on | 20020910 | |
Customizing Attributes | ORPM_PROJECT_STAT | Define Portfolio Item Alerts |
Customizing Activity | ORPM_PROJECT_STAT | Define Portfolio Item Alerts |
Document
Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
Document Name | ORPM_PROJECT_STAT |
Use
In this Customizing activity, you define portfolio item alerts to define the status of a portfolio item according to the following:
- Budget
- Priority
- Risk
- Schedule
Requirements
Standard settings
Activities
To configure the portfolio item alerts according to your requirements, proceed as follows:
- Double-click Budget Groups, Priority Groups, Risk Groups, and Schedule Groups in turn and do the following:
- Enter appropriate percentage values for upper and lower limits.
- Select the alert icons you wish to use.
At present, you must only use the red, yellow, and green LEDs.
- Select the status colors you want to use.
You can determine values for each portfolio item alert as follows:
- Budget
The budget status is based on the ratio of total actual cost to total planned cost. This data is transferred to SAP Portfolio and Project Management through the SAP FI/CO interfacing process and is displayed on the Project Details screen.
The total actual cost is the sum of all actual costs posted in SAP FI/CO on the portfolio item cost collectors over the complete posting period of the associated PS project element.
The formula is:
- For total planned cost > total actual cost (that is, under-budget portfolio item):
- budget ratio = (total actual cost - total budget cost ) / total actual cost * 100
- For total planned cost <= total actual cost (that is, over-budget/on-budget portfolio item):
- budget ratio = (total actual cost - total budget cost ) / total budget cost * 100
To use period-to-date costs in the budget icon calculations instead of total actual costs, you can implement BAdI: Calculation of Portfolio Item Alerts.
- Priority
The priority is derived directly from the following priority groups and is displayed in the portfolio item dashboard:
- Very High
- High
- Medium
- Low
- Risk
The risk status is based on the probability of technical/commercial success, and is displayed in the portfolio item dashboard.
The formula is:
(100 # ((probability of technical success + probability of commercial success) / 2))
- Schedule
The schedule status is based on the ratio of completed tasks to date to all tasks to be completed to date. Each task is weighted by the number of planned hours it takes to complete and the percentage completion of the task.
- Staffing
The staffing status is determined by calculating the difference between total demand (for all roles) and total assignment (assignments for all roles) for this item with a given assignment unit within the following 12 months.
The formula is as follows:
- Assignment = 0 status: red
- 0 < Assignment < Demand status: yellow
- Assignment = Demand status: green
- Assignment > Demand status: yellow or red
Example
The following is an example configuration for budget groups:
Budget Status Group Budget Status Group Text UpperLimit LowerLimit + + + Status Color
01 Critical Over budget 999 50 Red LED; stop; errors Red LED; stop; error Red default
02 Over Budget 49 20 Yellow LED; caution Yellow LED; caution Yellow default
03 On Budget 19 19 Green LED; go; ok Green LED; go; ok Green default
04 Under Budget 20- 49- Yellow LED; caution Yellow LED; caution Yellow default
05 Critical Under Budget 50- 999- Red LED; stop; errors Red LED; stop; errors Red default
Business Attributes
ASAP Roadmap ID | 201 | Make global settings |
Mandatory / Optional | 1 | Mandatory activity |
Critical / Non-Critical | 1 | Critical |
Country-Dependency | A | Valid for all countries |
Assigned Application Components
Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
---|---|---|---|---|
SIMG | ORPM_PROJECT_STAT | 0 | /RPM/XSD0000011 | Portfolio Management |
Maintenance Objects
Maintenance object type | C | Customizing Object |
Assigned objects | ||||||
---|---|---|---|---|---|---|
Customizing Object | Object Type | Transaction Code | Sub-object | Do not Summarize | Skip Subset Dialog Box | Description for multiple selections |
V_RPM_PROJ_STAT | C - View cluster | SM34 |
History
Last changed by/on | SAP | 20060519 |
SAP Release Created in | 100 |