SAP ABAP IMG Activity GRPC_EXTDUEDATEREVAL (Extend Due Date for Repeat Assessment and Test)
Hierarchy
GRCFND_A (Software Component) GRC Foundation ABAP
   GRC-SPC (Application Component) Process Controls
     GRPC_CUSTOMIZING (Package) Customizing
IMG Activity
ID GRPC_EXTDUEDATEREVAL Extend Due Date for Repeat Assessment and Test  
Transaction Code S_GR4_71000092   (empty) 
Created on 20081215    
Customizing Attributes GRPC_EXTDUEDATEREVAL   Extend Due Date for Repeat Assessment and Test 
Customizing Activity GRPC_EXTDUEDATEREVAL   Extend Due Date for Repeat Assessment and Test 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name GRPC_EXTDUEDATEREVAL    

Use

In this Customizing activity, you specify how the due date for a reevaluation task is determined. You select a particular number of days for reassessment and retest. Then the due date is recalculated and extended accordingly.

The due date for the reevaluation (for example, repeat test of effectiveness, repeat control design assessment, and so forth) is calculated as follows:

It is the latest date of the original due date, the date trigger of the reassessment or retest (which takes into account the time lag, if any), and the remediation due date plus the number of days which you specify here in the Due DT Ex. column.

Standard settings

The extended days are set to 0 in the standard system for each evaluation type. This means no additional extension of the due date for reevaluations is added.

Activities

You can only change the number of days of the extension for the entries provided in this Customizing activity.

Then save your entry.

Example

The user plans a self-assessment at the end of this year with the initial due date set to December 1. Issues have been reported, and the due date of the remediation plan is December 7. All issues were actually resolved and closed on December 8. A reassessment is required and the task is triggered immediately.

The user wants the due date of a repeat self-assessment to be 10 days after the latest date of the original due date, the remediation due date and the close of all issues. The extended days are set here to 10 days. Then the new due date of the Self-Reassessment is December 8 plus 10; that is, December 18.

Business Attributes
ASAP Roadmap ID 201   Make global settings 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG GRPC_EXTDUEDATEREVAL 0 GR11000001 Process Controls 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
V_GRPCASDUEDATE_VAR V - View SM30  
History
Last changed by/on SAP  20090123 
SAP Release Created in 300