SAP ABAP IMG Activity GRPC_AANDT_SPECREPTE (Specify Repeat Testing Necessity)
Hierarchy
GRCFND_A (Software Component) GRC Foundation ABAP
   GRC-SPC (Application Component) Process Controls
     GRPC_CUSTOMIZING (Package) Customizing
IMG Activity
ID GRPC_AANDT_SPECREPTE Specify Repeat Testing Necessity  
Transaction Code S_GR4_98000007   (empty) 
Created on 20080621    
Customizing Attributes GRPC_AANDT_SPECREPTE   Specify Repeat Testing Necessity 
Customizing Activity GRPC_AANDT_SPECREPTE   Specify Repeat Testing Necessity 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name GRPC_SPECIFY_REPEAT_TESTING    

Use

In this Customizing activity, you specify whether a reevaluation is required or not after all issues are closed. This also includes, as an option, setting the time lag for a reevaluation. It is common that reevaluations are performed only after there is sufficient data after remediation was completed.

This function provides a method for adjusting the time lag for the reevaluation based upon the frequency of operation of the control.

Requirements

Standard settings

The reevaluation settings are all active in the standard system. No time lags are created, so if reassessment or retest is enabled, the reassessment or retest tasks are sent immediately after all issues for an evaluation are closed.

Activities

  1. Go to the activity node and select Activate for the evaluation if you wish the reevaluation workflow to be sent after all issues are closed. If you do not want a reevaluation, ensure that Activate is not selected.
  2. Optional - Double-click the Frequency-Time lag node. Click the New Entry button, input the frequency and maintain the time lag according to the frequency.
  3. If you have not provided time lag settings, the activated reassessment or retest occurs immediately after all issues are closed. If you have provided time lag settings, the system takes these into account based upon the Frequency field in the control and the Time Lag as configured.

Example

Retest of Control Effectiveness    Frequency    Activated Time Lag

0DAY    Daily        15

0WEK     Weekly        21

0MON    Monthly        61

For a control with a frequency of "daily", the retest task is set 15 days after all issues for the control are closed.

Note: Any frequencies which are not set up or are created with a time lag of 0 are retested immediately after all issues for the control are closed.

Business Attributes
ASAP Roadmap ID 201   Make global settings 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
VC_GRPCREPWORK C - View cluster SM34  
History
Last changed by/on SAP  20081202 
SAP Release Created in 300