SAP ABAP IMG Activity CPRO_SAP_SETTINGS (Override Default Global Settings)
Hierarchy
CPRXRPM (Software Component) SAP Portfolio and Project Management 6.0
   PPM-PRO (Application Component) Project Management
     DEVELOPMENT_PROJECTS_CUSTOMIZE (Package) General Customizing for Project Management
IMG Activity
ID CPRO_SAP_SETTINGS Override Default Global Settings  
Transaction Code S_X1D_36000084   (empty) 
Created on 20120327    
Customizing Attributes CPRO_SAP_SETTINGS   Override Default Global Settings 
Customizing Activity 0RPM_SAP_SETTINGS   General Application Settings (Default Settings) 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name CPRO_SAP_SETTINGS    

Use

In this Customizing activity, you can override the global settings delivered by SAP with your own preferred values.

Requirements

You have checked the global settings delivered by SAP in the previous Customizing activity Check Global Settings.

Standard settings

The following settings are relevant to Project Management:

  • Area 0002 - Master Switches

Setting    Description    SAP Default    Possible Values

0008    Enhanced Capital and Resource Mgmt Switch (see SAP Note 1457426)    ' ' (Off)    X (On), ' ' (Off)

0015    Filter for Milestone Tasks    X (On)    X (On), ' ' (Off)

Filter for Milestone Tasks

In the Structure view of a project or the multi-project monitor, you can filter milestone tasks by setting the corresponding indicator in the filter. If you activate this switch, all other project element types are deselected automatically so that only tasks are filtered.
If you do not activate this switch, all project element types are filtered unless you deselect them manually.

  • Area 0006 - User Interface Settings

Setting    Description    SAP Default    Possible Values

0025    Enhanced Resource Availability Maintenance    ' ' (No)    X (Yes), ' ' (No)

  • Area 0007 - General Default Values

Setting    Description    SAP Default    Possible Values

0027    Check-in/Check-out of Documents     ' ' (Normal)    X (HTTP-Based),

            ' ' (Normal)

0041    Activate Fixed Values for Milestones    ' ' (No)    X(Yes), ' ' (No)

Activate Fixed Values for Milestones

If you activate this setting, fixed values are assigned automatically to the following attributes when you create a milestone task in an operational project or a project template: The duration is set to 1, the finish constraints and date are cleared, and the planned work is set to 0. This enables you to treat milestones as a single point in time.

In the Customizing activity Set Up Field Control, you can ensure that the fixed values are not changed in the project or project template. Adjust your field control for these fields using the additional condition C050 (Task is Milestone).

If you want to use your own fixed values instead of the standard values, implement the method SET_DATA_EXT in the Customizing activity BAdI: Check/Change Fields in Project Management.

Activities

Create entries for the default settings you want to override and enter your own preferred value in the Settings Value column.

Example

Business Attributes
ASAP Roadmap ID 201   Make global settings 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG CPRO_SAP_SETTINGS 0 APL0000008 Project Management 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
V_RPM_SET_VAL_C V - View SM30  
History
Last changed by/on SAP  20120327 
SAP Release Created in 500_702