Hierarchy
⤷ PPM-PFM (Application Component) Portfolio Management
⤷ RPM_IMG (Package) RPM IMG Objects
IMG Activity
ID | 0RPM_PLMPSINTEG | SAP PLM PS Integration Overview |
Transaction Code | S_PCC_47000004 | (empty) |
Created on | 20050822 | |
Customizing Attributes | 0RPM_PLMPSINTEG | SAP PLM PS Integration Overview |
Customizing Activity |
Document
Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
Document Name | 0RPM_PLMPSINTEG |
Use
This process describes how to integrate SAP Product Lifecycle Management - Project System (PLM PS) with SAP Portfolio and Project Management.
Importing Projects from SAP PLM PS to SAP Portfolio and Project Management
The nature of the data imported from SAP PLM PS to SAP Portfolio and Project Management depends on what the user selects in the front-end application. All data movement is controlled through the mapping table maintained in Customizing. Users can import tasks, roles, resources, and teams in any combination. These objects are transferred as they are maintained in the SAP PLM PS base system.
Before the import can take place, all configurations maintained in the SAP PLM PS base system must be transferred to SAP Portfolio and Project Management. This includes the project type, role types, and any specific configuration that determines how the data is stored or calculated.
Data transfer takes place as follows:
SAP PLM PS SAP Portfolio and Project Management
Project definition Project
WBS element Task
Network header Task
Network activity Task/role
Network activity element Task/role
Milestone Task
Activity milestone Task
Resource Resource
Work center Team
You can also transfer SAP PLM PS project data to the portfolio item by maintaining the mapping table entries in the relevant Customizing step.
Exporting Projects from SAP Portfolio and Project Management to SAP PLM PS
During export, a template must be selected from the SAP PLM PS base system. The selected template is copied and its start, end, and description are set as the SAP Portfolio and Project Management portfolio item planned start, planned finish, and description respectively.
Updating Projects in SAP Portfolio and Project Management
Once you have imported projects to SAP Portfolio and Project Management, you can update projects using the report Projects Batch Update Program (/RPM/PROJECTS_BATCH_UPDATE).
For more information, see the documentation for this report.
Requirements
Standard settings
Activities
To configure SAP Portfolio and Project Management to work with SAP PLM PS, perform the following steps:
- Create RFC Connections.
- Define Logical Systems
- Define Object Link Type Groupings
- Define Object Link Types
- Assign Base System Applications to Application Areas
- Assign Object Link Type Groupings to Applications
- Assign Fields for Import to Project Management
- Assign Fields for Export from Project Management
- Map Base System Object Fields to Portfolio Item Fields
- Map Portfolio Item Fields to Base System Fields
Example
Business Attributes
ASAP Roadmap ID | 201 | Make global settings |
Mandatory / Optional | 1 | Mandatory activity |
Critical / Non-Critical | 1 | Critical |
Country-Dependency | A | Valid for all countries |
Assigned Application Components
Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
---|---|---|---|---|
SIMG | 0RPM_PLMPSINTEG | 0 | /RPM/XSD0000011 | Portfolio Management |
Maintenance Objects
Maintenance object type |
History
Last changed by/on | SAP | 20051027 |
SAP Release Created in | 400 |