SAP ABAP IMG Activity 0RPM_CAPPLANSETTINGS (Define Capacity Planning Settings)
Hierarchy
CPRXRPM (Software Component) SAP Portfolio and Project Management 6.0
   PPM-PFM (Application Component) Portfolio Management
     RPM_IMG (Package) RPM IMG Objects
IMG Activity
ID 0RPM_CAPPLANSETTINGS Define Capacity Planning Settings  
Transaction Code S_PCC_47000019   (empty) 
Created on 20051026    
Customizing Attributes 0RPM_CAPPLANSETTINGS   Define Capacity Planning Settings 
Customizing Activity 0RPM_CAPPLANSETTINGS   Define Capacity Planning Settings 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name 0RPM_CAPPLANSETTINGS    

Use

In this Customizing activity, you can define the necessary mapping for the capacity planning. The following sets of mapping are available:

  1. Map capacity view to cost elements: the data from SAP FI systems are filled to the capacity groups based on the cost element (Cost Category From and Cost Category To) defined in the mapping.
  2. Map capacity view to role functions: the mapping is defined for the underlying Project Management projects. The groups are mapped to the role functions and data from the Project Management projects is taken into account depending on the mapping.

Requirements

Standard settings

There is no default configuration.

Activities

You can make the following settings:

  • Define and edit the cost elements to which the capacity view type has to be assigned.

    To do so, you enter the required range of cost elements (Cost Category From and Cost Category To).

  • Define and edit the mapping between the role function ID and the capacity view type.

    To do this, you enter the required range of role functions (ID of Role Function From and ID of Role Function To).

In a portfolio item, the following sets of dates are defined. For the integration and planning process, the start and finish are taken into account in the following sequence of priority:

  1. Actual
  2. Planned
  3. Forecasted

The data from the Project Management project to the portfolio item is taken into account within the time frame of the item dates.

Reports

  1. Execute the report /RPM/PLAN_INT_PREP to create financial and capacity categories and groups for the bucket or the portfolio items based on the parameters mentioned in the selection screen.
  2. Execute the report /RPM/CAP_PLAN_INT to perform the capacity planning for the different portfolio items based on the parameters mentioned in the selection screen.
  3. Execute the report /RPM/BUCKET_ROLLUP to roll up the capacity data for the different categories and groups of the portfolio items to its higher-level buckets.

Example

A role which is maintained from 01 JUL to 31 AUG with a capacity demand of 100 days and the portfolio item is maintained from 01 AUG to 31 AUG.

In this case, the item only reads the demand from the role that is within the time frame of the item, for example, from 01 AUG to 31 AUG. This means 50 days are stored in the capacity planning for the portfolio item.

Business Attributes
ASAP Roadmap ID 201   Make global settings 
Mandatory / Optional 1   Mandatory activity 
Critical / Non-Critical 1   Critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG 0RPM_CAPPLANSETTINGS 0 /RPM/XSD0000011 Portfolio Management 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
/RPM/VC_CAP_SET C - View cluster SM34  
History
Last changed by/on SAP  20051026 
SAP Release Created in 400