SAP ABAP Table BAPI_ACT_ELEMENT (BAPI Structure for Activity Elements)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PS-ST-OPR (Application Component) Operative Structures
     CNIF (Package) External 'Interface for Project Management System (PS)'
Basic Data
Table Category INTTAB    Structure 
Structure BAPI_ACT_ELEMENT   Table Relationship Diagram
Short Description BAPI Structure for Activity Elements    
Delivery and Maintenance
Pool/cluster      
Delivery Class      
Data Browser/Table View Maintenance     Display/Maintenance Allowed with Restrictions 
Components
     
Field Key Data Element Domain Data
Type
Length Decimal
Places
Short Description Check
table
1 NETWORK NW_AUFNR AUFNR CHAR 12   0   Network number *
2 ACTIVITY CN_VORNR VORNR CHAR 4   0   Activity number in network and standard network  
3 ELEMENT CN_ELEMENT VORNR CHAR 4   0   Activity element number (work/external/general costs)  
4 CONTROL_KEY STEUS STEUS CHAR 4   0   Control key *
5 WORK_CNTR ARBPL ARBPL CHAR 8   0   Work center  
6 PLANT WERKS_D WERKS CHAR 4   0   Plant *
7 DESCRIPTION LTXA1 TEXT40 CHAR 40   0   Operation short text  
8 VENDOR_NO LIFNR LIFNR CHAR 10   0   Account Number of Vendor or Creditor *
9 PRICE PREIS WERT11 CURR 11   2   Price  
10 PRICE_UNIT PEINH PACK3 DEC 5   0   Price unit  
11 COST_ELEM KSTAR KSTAR CHAR 10   0   Cost Element *
12 CURRENCY WAERS WAERS CUKY 5   0   Currency Key *
13 CURRENCY_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
14 INFO_REC INFNR INFNR CHAR 10   0   Number of purchasing info record *
15 PURCH_ORG EKORG EKORG CHAR 4   0   Purchasing organization *
16 PUR_GROUP EKGRP EKGRP CHAR 3   0   Purchasing group *
17 MATL_GROUP MATKL MATKL CHAR 9   0   Material Group *
18 NUMBER_OF_CAPACITIES ANZKAP INT1 INT1 3   0   Number of capacities required  
19 PERCENT_OF_WORK APROZENT INT1 INT1 3   0   Work percentage  
20 ACTTYPE LSTAR LSTAR CHAR 6   0   Activity Type *
21 ACTIVITY_COSTS PRKST PRKST CURR 11   2   Costs in the activity  
22 PROJECT_DEFINITION PS_PSPID PS_PSPID CHAR 24   0   Project definition  
23 WBS_ELEMENT PS_POSID PS_POSID CHAR 24   0   Work Breakdown Structure Element (WBS Element)  
24 DISTRIBUTING_KEY CR_VERTN CR_VERTL CHAR 8   0   Distr.cap.reqmts (plant maint.,process order, network) *
25 TAXJURCODE TXJCD TXJCD CHAR 15   0   Tax Jurisdiction *
26 PROFIT_CTR PRCTR PRCTR CHAR 10   0   Profit Center *
27 NOT_MRP_APPLICABLE NODISP XFELD CHAR 1   0   Ind: Reserv. not applicable to MRP;Purc. req. not created  
28 PROJECT_SUMMARIZATION CLASF XFELD CHAR 1   0   Ind.: Take Activity Into Account for Project Summarization  
29 OPERATION_MEASURE_UNIT VORME MEINS UNIT 3   0   Unit of measure for activity *
30 OPERATION_MEASURE_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
31 PLND_DELRY PLIFZ DEC3 DEC 3   0   Planned delivery time in days  
32 WORK_ACTIVITY ARBEIT ARBEIT QUAN 7   1   Work involved in the activity  
33 UN_WORK ARBEITE MEINS UNIT 3   0   Unit for work *
34 UN_WORK_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
35 EARLY_START_DATE FSAVD DATUM DATS 8   0   Earliest scheduled start: Execution (date)  
36 EARLY_START_TIME FSAVZ ATIME TIMS 6   0   Earliest scheduled start: Execution (time)  
37 EARLY_FINISH_DATE FSEDD DATUM DATS 8   0   Earliest scheduled finish: Execution (date)  
38 EARLY_FINISH_TIME FSEDZ ATIME TIMS 6   0   Earliest scheduled finish: Execution (time)  
39 LATEST_START_DATE SSAVD DATUM DATS 8   0   Latest scheduled start: Execution (date)  
40 LATEST_START_TIME SSAVZ ATIME TIMS 6   0   Latest scheduled start: Execution (time)  
41 LATEST_FINISH_DATE SSEDD DATUM DATS 8   0   Latest scheduled finish: Execution (date)  
42 LATEST_FINISH_TIME SSEDZ ATIME TIMS 6   0   Latest scheduled finish: Execution (time)  
43 USER_FIELD_KEY SLWID SLWID CHAR 7   0   Key word ID for user-defined fields *
44 USER_FIELD_CHAR20_1 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
45 USER_FIELD_CHAR20_2 USRCHAR20 USRCHAR20 CHAR 20   0   User field with 20 characters  
46 USER_FIELD_CHAR10_1 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
47 USER_FIELD_CHAR10_2 USRCHAR10 USRCHAR10 CHAR 10   0   User field with 10 characters  
48 USER_FIELD_QUAN1 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
49 USER_FIELD_UNIT1 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
50 USER_FIELD_UNIT1_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
51 USER_FIELD_QUAN2 USRQUAN13 USRQUAN13 QUAN 13   3   User field for quantity (length 10.3)  
52 USER_FIELD_UNIT2 USRUNIT MEINS UNIT 3   0   User field: Unit for quantity fields *
53 USER_FIELD_UNIT2_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
54 USER_FIELD_CURR1 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
55 USER_FIELD_CUKY1 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
56 USER_FIELD_CUKY1_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
57 USER_FIELD_CURR2 USRCURR13 USRCURR13 CURR 13   3   User-defined field for values (length 10,3)  
58 USER_FIELD_CUKY2 USRCUKY WAERS CUKY 5   0   User field: Unit for value fields *
59 USER_FIELD_CUKY2_ISO ISOCD ISOCD CHAR 3   0   ISO currency code  
60 USER_FIELD_DATE1 USRDATE USRDATE DATS 8   0   User field for date  
61 USER_FIELD_DATE2 USRDATE USRDATE DATS 8   0   User field for date  
62 USER_FIELD_FLAG1 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
63 USER_FIELD_FLAG2 USRFLAG FLAG CHAR 1   0   User-defined field: Indicator for reports  
64 EARLY_START_DATE_FC FPAVD DATUM DATS 8   0   Earliest scheduled start date (forecast)  
65 EARLY_START_TIME_FC FPAVZ ATIME TIMS 6   0   Earliest scheduled start time (forecast)  
66 EARLY_FINISH_DATE_FC FPEDD DATUM DATS 8   0   Earliest scheduled finish date (forecast)  
67 EARLY_FINISH_TIME_FC FPEDZ ATIME TIMS 6   0   Earliest scheduled finish time (forecast)  
68 LATEST_START_DATE_FC SPAVD DATUM DATS 8   0   Latest scheduled start date (forecast)  
69 LATEST_START_TIME_FC SPAVZ ATIME TIMS 6   0   Latest scheduled start time (forecast)  
70 LATEST_FINISH_DATE_FC SPEDD DATUM DATS 8   0   Latest scheduled finish date (forecast)  
71 LATEST_FINISH_TIME_FC SPEDZ ATIME TIMS 6   0   Latest scheduled finish time (forecast)  
72 OBJECTCLASS_EXT SCOPE_LD CHAR5 CHAR 5   0   Object class, language-dependent  
73 OFFSET_START OFFSTB VNZTV QUAN 5   0   Offset to start of production resource/tool usage  
74 OFFSET_START_UNIT CP_OEHOFFB MEINS UNIT 3   0   Unit for offset to start *
75 OFFSET_START_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
76 OFFSET_END CP_OOFFSTE VNZTV QUAN 5   0   Offset to sub-operation finish  
77 OFFSET_END_UNIT CP_OEHOFFE MEINS UNIT 3   0   Unit for offset to finish *
78 OFFSET_END_UNIT_ISO ISOCD_UNIT ISOCD_UNIT CHAR 3   0   ISO code for unit of measurement *
79 FUNC_AREA FKBER_SHORT FKBER_SHORT CHAR 4   0   Functional Area  
80 FUNC_AREA_LONG FKBER FKBER CHAR 16   0   Functional Area *
81 PERS_NO CO_PERNR PERNR NUMC 8   0   Personnel number  
History
Last changed by/on SAP  20130529 
SAP Release Created in