SAP ABAP Table NTWXPD_DATA (Progress Tracking for Network Activities)
Hierarchy
☛
EA-APPL (Software Component) SAP Enterprise Extension PLM, SCM, Financials
⤷ PS-PRG-TRC (Application Component) Progress Tracking
⤷ EXPD (Package) Expediting for Order
⤷ PS-PRG-TRC (Application Component) Progress Tracking
⤷ EXPD (Package) Expediting for Order
Basic Data
Table Category | INTTAB | Structure |
Structure | NTWXPD_DATA | Table Relationship Diagram |
Short Description | Progress Tracking for Network Activities |
Delivery and Maintenance
Pool/cluster | ||
Delivery Class | ||
Data Browser/Table View Maintenance | Display/Maintenance Allowed with Restrictions |
Components
Field | Key | Data Element | Domain | Data Type |
Length | Decimal Places |
Short Description | Check table |
|
---|---|---|---|---|---|---|---|---|---|
1 | PSPID | PS_PSPID | PS_PSPID | CHAR | 24 | 0 | Project definition | ||
2 | POSID | PS_POSID | PS_POSID | CHAR | 24 | 0 | Work Breakdown Structure Element (WBS Element) | ||
3 | AUFNR | AUFNR | AUFNR | CHAR | 12 | 0 | Order Number | * | |
4 | VORNR | VORNR | VORNR | CHAR | 4 | 0 | Operation/Activity Number | ||
5 | LTXA1 | LTXA1 | TEXT40 | CHAR | 40 | 0 | Operation short text | ||
6 | FSAVD | FSAVD | DATUM | DATS | 8 | 0 | Earliest scheduled start: Execution (date) | ||
7 | FSAVZ | FSAVZ | ATIME | TIMS | 6 | 0 | Earliest scheduled start: Execution (time) | ||
8 | FSEDD | FSEDD | DATUM | DATS | 8 | 0 | Earliest scheduled finish: Execution (date) | ||
9 | FSEDZ | FSEDZ | ATIME | TIMS | 6 | 0 | Earliest scheduled finish: Execution (time) | ||
10 | SSAVD | SSAVD | DATUM | DATS | 8 | 0 | Latest scheduled start: Execution (date) | ||
11 | SSAVZ | SSAVZ | ATIME | TIMS | 6 | 0 | Latest scheduled start: Execution (time) | ||
12 | SSEDD | SSEDD | DATUM | DATS | 8 | 0 | Latest scheduled finish: Execution (date) | ||
13 | SSEDZ | SSEDZ | ATIME | TIMS | 6 | 0 | Latest scheduled finish: Execution (time) | ||
14 | ISDD | ISDD | DATUM | DATS | 8 | 0 | Actual start: Execution (date) | ||
15 | ISDZ | ISDZ | ATIME | TIMS | 6 | 0 | Actual start: Execution/setup (time) | ||
16 | IEDD | IEDD | DATUM | DATS | 8 | 0 | Actual finish: Execution (date) | ||
17 | IEDZ | IEDZ | ATIME | TIMS | 6 | 0 | Actual finish: Execution (time) | ||
18 | CO_PEDD | CO_PEDD | DATUM | DATS | 8 | 0 | Forecast finish date of operation from confirmation | ||
19 | CO_PEDZ | CO_PEDZ | ATIME | TIMS | 6 | 0 | Forecast finish time of operation from confirmation | ||
20 | EPANF | EPANF | DATUM | DATS | 8 | 0 | Dispatched start date for operation | ||
21 | EPANZ | EPANZ | ATIME | TIMS | 6 | 0 | Dispatched start time for operation | ||
22 | EPEND | EPEND | DATUM | DATS | 8 | 0 | Dispatched finish date | ||
23 | EPENZ | EPENZ | ATIME | TIMS | 6 | 0 | Dispatched finish time | ||
24 | CO_DAUBEA | CO_DAUBEA | DAUER_6_1 | QUAN | 7 | 1 | Processing time | ||
25 | BEAZE | BEAZE | EINHEIT | UNIT | 3 | 0 | Unit of measure for processing time | ||
26 | ARBEIT | ARBEIT | ARBEIT | QUAN | 7 | 1 | Work involved in the activity | ||
27 | ARBEITE | ARBEITE | MEINS | UNIT | 3 | 0 | Unit for work | * | |
28 | CO_ISMNW | CO_ISMNW | MENG13 | QUAN | 13 | 3 | Actual work | ||
29 | PDAU | PDAU | DAUER_4_1 | QUAN | 5 | 1 | Forecasted duration of activity from confirmation | ||
30 | PDAE | PDAE | MEINS | UNIT | 3 | 0 | Unit of the forecasted duration from the confirmation | * | |
31 | OFMNW | OFMNW | ARBEIT | QUAN | 7 | 1 | Forecasted work (actual + remaining) |
History
Last changed by/on | SAP | 20100310 |
SAP Release Created in | 602 |