SAP ABAP Data Element VPWRK (Planning plant)
Hierarchy
BBPCRM (Software Component) BBPCRM
   PP-MP-DEM (Application Component) Demand Management
     MDPB (Package) Application development R/3 purchasing
Basic Data
Data Element VPWRK
Short Description Planning plant  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type WERKS    
Data Type CHAR   Character String 
Length 4    
Decimal Places 0    
Output Length 4    
Value Table T001W    
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name PLNG_PLANT   
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Plng plant 
Medium 15 Planning plant 
Long 20 Planning plant 
Heading PPlt 
Documentation

Definition

Key which specifically identifies the plant from which the planned independent requirements of the reference material comes from.

Use

You maintain planned independent requirements for the planning material entered here. If a sales order/customer requirement is posted for the material in question, the sales order quantity consumes the planned independent requirements of the planning material. The planning material is not actually produced itself. If is only used for planning non-variant parts and for consuming the planned independent requirements.

Note

In this planning strategy, the system uses the consumption mode maintained for the planning material to determine how many days into the future or the past consumption is to be carried out. The means that you must maintain the consumption mode for this strategy must be maintained in the material master record.

Example

The material master record 4711 contains the material 4712 as a planning material. The planning material contains the BOM with the non-variant parts. You create planned independent requirements for material 4712. When creating a sales order for material 4711, the system realizes that material 4712 is the planning material for material 4711. Then the sales order for material 4711 consumes the planned independent requirements of material 4712.

Dependencies

A valid material master record must exist for the planning material in the planning plant. The material master record of the planning material cannot contain a planning material as this procedure can only be carried out at single-level.

History
Last changed by/on SAP  19991102 
SAP Release Created in