SAP ABAP Data Element PS_PSPNA (Assign new activities to networks that are assigned to WBS)
Hierarchy
☛
SAP_APPL (Software Component) Logistics and Accounting
⤷ PS-ST-OPR-PPB (Application Component) Project Planning Board
⤷ CN_PPT_GRAFIK (Package) Project Planning Board
⤷ PS-ST-OPR-PPB (Application Component) Project Planning Board
⤷ CN_PPT_GRAFIK (Package) Project Planning Board
Basic Data
Data Element | PS_PSPNA |
Short Description | Assign new activities to networks that are assigned to WBS |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | XFELD | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | Act to WBS |
Medium | 15 | Act to WBS netw |
Long | 20 | New act. to WBS netw |
Heading | 3 | AWB |
Documentation
Definition
Specifies that when you create a new activity, it is assigned to one of the networks assigned to the WBS element. The system determines the networks that have been assigned to the WBS element only from the network headers.
If this indicator is not set, a list of all the networks that have been assigned (via network header and otherwise) to the WBS element is displayed from which you can select a network.
Dependencies
The indicator takes effect, if the key for network assignment has been set to For WBS element in the project profile, or if in structure planning/project planning board the indicator Networks to WBS elementshas been set by choosing Settings -> Options.
The system proceeds as follows when you create a new activity for a WBS element:
- If no network has been assigned to the WBS element, a new network is generated. This also happens, if activities from other networks have been assigned to the WBS element by moving activities from other networks.
- If several network headers have been assigned to the WBS element, only these are presented for selection.
History
Last changed by/on | SAP | 19980706 |
SAP Release Created in |