SAP ABAP Data Element MD_PLIFZ_DB (Consider Planned Delivery Time of the MRP Area)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   MM-CBP (Application Component) Consumption-Based Planning (See Also PP-MRP)
     MD06 (Package) Development Material Requirements Planning
Basic Data
Data Element MD_PLIFZ_DB
Short Description Consider Planned Delivery Time of the MRP Area  
Data Type
Category of Dictionary Type D   Domain
Type of Object Referenced     No Information
Domain / Name of Reference Type MD_PLIFZ_DB    
Data Type CHAR   Character String 
Length 1    
Decimal Places 0    
Output Length 1    
Value Table      
Further Characteristics
Search Help: Name    
Search Help: Parameters    
Parameter ID   
Default Component name    
Change document    
No Input History    
Basic direction is set to LTR    
No BIDI Filtering    
Field Label
  Length  Field Label  
Short 10 Cnsd PlDTi 
Medium 18 Consider PlDelTime 
Long 30 Consider Planned Delivery Time 
Heading  
Documentation

Definition

Indicator that determines whether the planned delivery time is used in the MRP area.

Use

Procedure

You have maintained a planned delivery time in the MRP area. If the planned delivery time for the MRP area is to be used for the external procurement of material for the MRP area, you must set the value "Use Planned Delivery Time MRP Area". Otherwise, the planned delivery time of the plant will be used.

Examples

Dependencies

For stock transport requisitions (plant to a storage location MRP area of the same plant) the planned delivery time of the MRP area is only used if the indicator "Consider Planned Delivery Time" is set.