SAP ABAP Data Element ADPM_IPRLOP (CMC: Use Parallel Ops f. 1 Activity (Labor/Machine))
Hierarchy
☛
ECC-DIMP (Software Component) DIMP
⤷ IS-AD (Application Component) Aerospace & Defence Industry Solution
⤷ AD_ROT_PRIO (Package) A&D : Rotable Control ( CMC )
⤷ IS-AD (Application Component) Aerospace & Defence Industry Solution
⤷ AD_ROT_PRIO (Package) A&D : Rotable Control ( CMC )
Basic Data
Data Element | ADPM_IPRLOP |
Short Description | CMC: Use Parallel Ops f. 1 Activity (Labor/Machine) |
Data Type
Category of Dictionary Type | D | Domain |
Type of Object Referenced | No Information | |
Domain / Name of Reference Type | XFELD | |
Data Type | CHAR | Character String |
Length | 1 | |
Decimal Places | 0 | |
Output Length | 1 | |
Value Table |
Further Characteristics
Search Help: Name | ||
Search Help: Parameters | ||
Parameter ID | ||
Default Component name | ||
Change document | ||
No Input History | ||
Basic direction is set to LTR | ||
No BIDI Filtering |
Field Label
Length | Field Label | |
Short | 10 | ParallelOp |
Medium | 19 | Parallel Operations |
Long | 40 | Parallel Ops (Combine Labor/Machine) |
Heading | 43 | Parallel Operations (Combine Labor/Machine) |
Documentation
Definition
Combines labor and machine operations that belong together internally.
At runtime the CMC bundles the operations, determines which has the longest duration and sets this duration for both the labor and the machine operation. This is an improvement to the standard CS functionality, which only makes a 50/50 split of labor and machine when evaluating capacity.
Procedure
Select the indicator to split labor and machine work into separate operations.
Examples
Operation 10 and 20 have duration 5 and 3 hours respectively. They belong together. The first is the labor operation, the second is the machine operation. The machine operation is flagged. At runtime the CMC groups these two operations and sets the duration of both operations to 5 hours.
Dependencies
History
Last changed by/on | SAP | 20050301 |