SAP ABAP IMG Activity SIMG_CFMENUORKEKEG7 (Set Up Indirect Allocation of Activities from Cost Centers/Processes)
Hierarchy
BBPCRM (Software Component) BBPCRM
   CRM (Application Component) Customer Relationship Management
     CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
       KE0C (Package) Customizing for Profitability Analysis
IMG Activity
ID SIMG_CFMENUORKEKEG7 Set Up Indirect Allocation of Activities from Cost Centers/Processes  
Transaction Code S_ALR_87005781   IMG Activity: SIMG_CFMENUORKEKEG7 
Created on 19981222    
Customizing Attributes SIMG_CFMENUORKEKEG7   Set Up Indirect Allocation of Activities from Cost Centers/Processes 
Customizing Activity SIMG_CFMENUORKEKEG7   Set Up Indirect Allocation of Activities from Cost Centers/Processes 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name SIMG_CFMENUORKEKEG7    

The advantage of indirect activity allocation over cost assessment is that you can allocate the entire activity based on the activity quantity performed or one determined indirectly after valuating it with a fixed and/or a variable price. For information on the basic concept of indirect activity allocation, see Indirect Activity Allocation.

Activities

  • Set up indirect activity allocation as described by performing the steps described in the section Define Indirect Activity Allocation in Customizing for Cost Center Accounting. You use the same steps again to set up the indirect allocation of activities from processes.
  • Enter a cost center and a suitable activity type or business process as the sender objects in the cycle.
  • As the receiver, specify those profitability segments that are relevant for the allocation of costs.

Prerequisites

For the indirect allocation of activities from cost centers:

  • You must have an activity type that uses allocation category 02 or 03.
    Maintain Activity Types for Indirect Activity Allocation.
  • Planning data must exist for the activity type so that
    • plan price iteration has been carried out, or
    • a plan price was defined manually for the cost center, or
    • an actual price must have been determined in period-end closing.

For the indirect allocation of activities from processes:

  • You must have Activity-Based Costing implemented as an operational Controlling component in your system
  • You need to have defined a process containing the allocation category 02 or 03.
  • The process has been planned during business process planning so that
    • a price is available for valuating utilization, or
    • an actual price is determined.

Notes on Planning

  • The receiver version of a cycle is achieved when you have performed the assignment to the sender version under Planning -> Integrated Planning -> Transfer Cost Center Planning/ Process Planning -> Initial Steps -> Assign Receiver Plan Version.
  • Note that the receiver controlling area should be the same as the sender controlling area. It is therefore important for the receiver rule "variable portions" that the characteristic "controlling area" has been planned in manual planning if allocation is to occur on the basis of planning data.

Business Attributes
ASAP Roadmap ID 204   Establish Functions and Processes 
Mandatory / Optional 2   Optional activity 
Critical / Non-Critical 1   Critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG SIMG_CFMENUORKEKEG7 0 HLA0100150 O  
SIMG SIMG_CFMENUORKEKEG7 1 I070004708 Profitability Analysis 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
KEG1 T - Individual transaction object KEG7 02 Create Indirect Plan Activity Allocation 
KEG1 T - Individual transaction object KEG8 0201 Change Indirect Plan Activity Allocation 
KEG1 T - Individual transaction object KEG9 0202 Display Indirect Plan Activity Allocation 
History
Last changed by/on SAP  19990701 
SAP Release Created in