SAP ABAP IMG Activity SIMG_CFMENUOPP1OMIW (Define BOM Explosion Control)
Hierarchy
SAP_APPL (Software Component) Logistics and Accounting
   PP-MRP-BD (Application Component) Master Data
     MD0C (Package) Customizing R/3 Material Requirements Planning
IMG Activity
ID SIMG_CFMENUOPP1OMIW Define BOM Explosion Control  
Transaction Code S_ALR_87005954   IMG Activity: SIMG_CFMENUOPP1OMIW 
Created on 19981222    
Customizing Attributes SIMG_CFMENUOPP1OMIW   Define BOM Explosion Control 
Customizing Activity SIMG_CFMENUOPP1OMIW   Define BOM Explosion Control 
Document
Document Class SIMG   Hypertext: Object Class - Class to which a document belongs.
Document Name SIMG_CFMENUOPP1OMIW    

Workstep Plant

In this workstep, you define the following plant-specific parameters:

  • the explosion date for BOM and routing selection
  • whether the planning run is to create dependent requirements for bulk material in the appropriate plant
  • whether the planning run is to check whether sales order BOMs exist in the corresponding plant

The explosion date determines which BOM (or which routing) is to be used for explosion in the planning run and, thus, for the calculation of the dependent requirements. This means, the system selects the BOM that is valid for the explosion date and creates dependent requirements for the components contained in this BOM.
The following possibilities are available for the explosion date:

  • BOM explosion number/order start date

    The system checks whether a BOM explosion number exists for the material or the planned order. If yes, the fixed key date recorded in the BOM explosion number is used as the explosion date. If no BOM explosion number has been determined, the order start date of the planned order is used as the explosion date.

  • BOM explosion number/order finish date

    The system checks whether a BOM explosion number exists for the material or the planned order. If yes, the fixed key date recorded in the BOM explosion number is used as the explosion date. If no BOM explosion number has been determined, the order finish date of the planned order is used as the explosion date.

  • only the order start date is valid as explosion date
  • only the order finish date is valid as explosion date

If you have set the indicator Exclude bulk material, no dependent requirements are created in the planning run for BOM items that are flagged as bulk materials. This reduces the system load.

If the indicator is not set, the system also creates dependent requirements for bulk materials that can only be displayed in the planned order for information purposes but are not included in the net requirements calculation. That is, they are not planned in the planning run and they are not displayed in the stock/requirements list.

If the indicator Procedure with sales order BOM/WBS BOM has been set, in the planning run, the system checks whether sales order BOMs or WBS BOMs exist for the materials to be planned. If these BOMs exist, the system explodes these BOMs.

If the indicator BOM explosion number make-to-order/engineer-to- order prod. has been set, in the net calculation, the system checks whether a BOM explosion number exists for the corresponding requirements. If make-to-order or engineer-to-order production is concerned, this BOM explosion number is copied to the receipt elements which are generated subsequently. The BOM explosion number is ignored in make-to-stock production.

Workstep MRP group

In this workstep, you define the following parameters, which are specific to the MRP group:

  • the explosion date for the BOM and routing selections

    If no indicator is set, the plant settings are copied.

  • whether the planning run for bulk material should generate dependent requirements for the MRP group concerned

    If no indicator is set, the plant settings are copied.

Example

Requirements

Standard settings

Recommendation

Activities

Set the parameters for the plant before setting the parameters for the MRP group.

Further notes

Business Attributes
ASAP Roadmap ID 204   Establish Functions and Processes 
Mandatory / Optional 3   Nonrequired activity 
Critical / Non-Critical 2   Non-critical 
Country-Dependency A   Valid for all countries 
Assigned Application Components
Documentation Object Class Documentation Object Name Current line number Application Component Application Component Name
SIMG SIMG_CFMENUOPP1OMIW 0 HLA0006451 Planning Execution 
Maintenance Objects
Maintenance object type C   Customizing Object 
Assigned objects
Customizing Object Object Type Transaction Code Sub-object Do not Summarize Skip Subset Dialog Box Description for multiple selections
V_T399D_S V - View OMIW 0000000000 BOM Explosion Control 
History
Last changed by/on SAP  19981222 
SAP Release Created in