Hierarchy
⤷ PP-PI-PMA (Application Component) Process Management
⤷ CMX_XS (Package) XSteps: Run Time Environment
IMG Activity
ID | COCR_PROF | Assign Standard XSteps to the Production Scheduling Profile |
Transaction Code | S_PLN_06000194 | (empty) |
Created on | 20030522 | |
Customizing Attributes | COCR_PROF | Assign Standard XSteps Production Scheduling Profile |
Customizing Activity | COCR_PROF | Assign Standard XSteps Production Scheduling Profile |
Document
Document Class | SIMG | Hypertext: Object Class - Class to which a document belongs. |
Document Name | COCR_PROF |
Use
In this activity, you can assign one or more standard XSteps to a production scheduling profile.
You normally define Execution Steps (XSteps) in the standard XStep repository or in the routing, which you then use to generate production orders. You can also reference or copy standard XSteps in the routing. If you do not want to reference a standard XStep in a routing, you can copy one or more standard XSteps into the production order via a production scheduling profile.
In this step, you specify that standard XSteps are automatically to be copied into the production order via a production scheduling profile when the production order is created.
Note
With this variant, you may have to perform context maintenance of the XSteps for operations in the individual production order yourself.
If you have both assigned standard XSteps to the production scheduling profile and maintained them in the routing, the system uses only the XSteps defined in the routing in the production order.
Note
You can also use this functionality for master recipes and process orders.
Requirements
You have defined a production scheduling profile and stored it in the material master record (view Work Scheduling) of the finished product that is to be produced.
- You define the production scheduling profile for PP production orders under:
Define Production Scheduling Profile - You define the production scheduling profile for PI process orders under:
Define Production Scheduling Profile
Activities
- Choose New Entries.
- Specify a production scheduling profile and the associated plant.
- Assign a standard XStep to the production scheduling profile.
- Save.
To assign further standard XSteps to the same production scheduling profile you must create a new entry for each additional standard XStep.
Example
Business Attributes
ASAP Roadmap ID | 204 | Establish Functions and Processes |
Mandatory / Optional | 2 | Optional activity |
Critical / Non-Critical | 2 | Non-critical |
Country-Dependency | A | Valid for all countries |
Assigned Application Components
Documentation Object Class | Documentation Object Name | Current line number | Application Component | Application Component Name |
---|---|---|---|---|
SIMG | COCR_PROF | 0 | HLA0009520 | Production Planning and Control |
Maintenance Objects
Maintenance object type | C | Customizing Object |
Assigned objects | ||||||
---|---|---|---|---|---|---|
Customizing Object | Object Type | Transaction Code | Sub-object | Do not Summarize | Skip Subset Dialog Box | Description for multiple selections |
V_COCR_CMX_CO43 | V - View | COCR_PROF |
History
Last changed by/on | SAP | 20070725 |
SAP Release Created in | 200 |