SAP ABAP Message Class BK Message Number 126 (Run schedule & is not created for material &/production version &)
Hierarchy
☛
BBPCRM (Software Component) BBPCRM
⤷ CRM (Application Component) Customer Relationship Management
⤷ CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷ KBAS (Package) Overhead Cost Controlling
⤷ CRM (Application Component) Customer Relationship Management
⤷ CRM_APPLICATION (Package) All CRM Components Without Special Structure Packages
⤷ KBAS (Package) Overhead Cost Controlling
Attribute
Message class | BK | ||
Short Description | Create, Display, Reverse Controlling Document | ||
Message Number | 126 | ||
Documentation status | |||
Authorization check Error Message | |||
Changed On |
Message Text
Run schedule & is not created for material &/production version &
Help Document
Diagnosis
Run schedule does not belong to the material /production version combination.
System Response
If you enter both a run schedule and a material/production version combination, the SAP System checks whether the run schedule also belongs to this production version.
If you enter either a run schedule or a material/production version combination only, the SAP System automatically fills the fields left blank.
Procedure
- Enter a different run schedule or a different material/production version combination, so that the run schedule belongs to the production version.
- Alternately, delete one or both entries.
History
Last changed on/by | 20100310 | SAP | |
SAP Release Created in |